Re: DragonFlyBSD 2.0 RELEASE SCHEDULE - Release will be on 20 July 2008

2008-07-22 Thread Jeremy C. Reed
 I have tested the patch on DragonFly, but this patch to 9.3.4 has had 
 little testing.
 
 Please test HEAD's named. See the commit message for details.

I see that http://www.dragonflybsd.org/community/release2_0.shtml says 
wrong version for BIND. I specifically didn't update to 9.3.5 as 
requested. I did apply patch from 9.3.5-P1 to existing 9.3.4-P1 and named 
it as 9.3.4-P2 (my invented name).


Re: DragonFlyBSD 2.0 RELEASE SCHEDULE - Release will be on 20 July 2008

2008-07-22 Thread Jeremy C. Reed
 I see that http://www.dragonflybsd.org/community/release2_0.shtml says 
 wrong version for BIND. I specifically didn't update to 9.3.5 as 
 requested. I did apply patch from 9.3.5-P1 to existing 9.3.4-P1 and named 
 it as 9.3.4-P2 (my invented name).

I see it listed wrong on webpage twice.


Re: DragonFlyBSD 2.0 RELEASE SCHEDULE - Release will be on 20 July 2008

2008-07-22 Thread Matthew Dillon

:
: I see that http://www.dragonflybsd.org/community/release2_0.shtml says 
: wrong version for BIND. I specifically didn't update to 9.3.5 as 
: requested. I did apply patch from 9.3.5-P1 to existing 9.3.4-P1 and named 
: it as 9.3.4-P2 (my invented name).
:
:I see it listed wrong on webpage twice.

Try that.

-Matt
Matthew Dillon 
[EMAIL PROTECTED]


Re: DragonFlyBSD 2.0 RELEASE SCHEDULE - Release will be on 20 July 2008

2008-07-12 Thread Trevor Kendall
2008/7/11 Matthew Dillon [EMAIL PROTECTED]:
Now is the time for people to list their must-haves and would-likes
for the release!  Please use this thread.  I'll start it off:

Fix du and large directories:

du -shc .data .data .data
458G.data
458G.data
458G.data
-673.8G total

I had a patch for this at one stage a long time ago, but I don't know
what happened to it. I won't have time to do this before Sunday though
(or anytime soon).


Re: DragonFlyBSD 2.0 RELEASE SCHEDULE - Release will be on 20 July 2008

2008-07-12 Thread Matthew Dillon

:Fix du and large directories:
:
:du -shc .data .data .data
:458G   .data
:458G   .data
:458G   .data
:-673.8Gtotal
:
:I had a patch for this at one stage a long time ago, but I don't know
:what happened to it. I won't have time to do this before Sunday though
:(or anytime soon).

Done!  I've committed a fix to HEAD.

-Matt
Matthew Dillon 
[EMAIL PROTECTED]


Re: DragonFlyBSD 2.0 RELEASE SCHEDULE - Release will be on 20 July 2008

2008-07-11 Thread Rumko
Matthew Dillon wrote:

 The release is scheduled for Sunday 20-July-2008!  We have about a week
 left!
 
 I will be branching the code base this Sunday (13-July-2008).
 HAMMER development through next week will continue to occur on HEAD
 and then be synced to 2.0 for the release.
 
 --
 
 We have a security issue with BIND that needs to be resolved, could
 someone take on that task?  I would prefer that just the patch be
 committed to the current code base if possible, I do not want to bring
 in a whole new BIND this late in the game.
 
 Now is the time for people to list their must-haves and would-likes
 for the release!  Please use this thread.  I'll start it off:
 
 * BIND security fix
 
 * PkgSrc binary packages build for the release
 
 Any takers for each of the above items?
 
 -Matt

Hmm, I'd like nataraid to be updated (there is a code bounty for it ... but
this might be a too big of a change for this release?) ... Don't know about
anyone else, but since HAMMER should work for non-root FS', I don't see
anything other that I'd really need in this release.

(well you did say Now is the time for people to list their must-haves and
would-likes for the release!)
-- 
Regards,
Rumko


Re: DragonFlyBSD 2.0 RELEASE SCHEDULE - Release will be on 20 July 2008

2008-07-11 Thread Jeremy C. Reed
On Fri, 11 Jul 2008, Matthew Dillon wrote:

 We have a security issue with BIND that needs to be resolved, could
 someone take on that task?  I would prefer that just the patch be
 committed to the current code base if possible, I do not want to bring
 in a whole new BIND this late in the game.

The patch for the issues from 9.3.5 to 9.3.5-P1 (minus win32 and doc) 
applies fine to your HEAD contrib/bind-9.3 (which is 9.3.4-P1) other than 
a few RCS ident conflicts.

The original patch is on pkgbox at /home/reed/9.3.5-P1.patch and the 
updated src is at /home/reed/dragonfly/src/contrib/bind-9.3/

I am doing a test build now on HEAD. Should I be testing with a specific 
tag?

I have tested the security fixes on DragonFly a few times (watching random 
source ports) but not built from DragonFly source yet.


Re: DragonFlyBSD 2.0 RELEASE SCHEDULE - Release will be on 20 July 2008

2008-07-11 Thread Matthew Dillon

:The patch for the issues from 9.3.5 to 9.3.5-P1 (minus win32 and doc) 
:applies fine to your HEAD contrib/bind-9.3 (which is 9.3.4-P1) other than 
:a few RCS ident conflicts.
:
:The original patch is on pkgbox at /home/reed/9.3.5-P1.patch and the 
:updated src is at /home/reed/dragonfly/src/contrib/bind-9.3/
:
:I am doing a test build now on HEAD. Should I be testing with a specific 
:tag?
:
:I have tested the security fixes on DragonFly a few times (watching random 
:source ports) but not built from DragonFly source yet.

HEAD is fine.  We don't branch until Sunday.

I'll leave it in your court then, please commit the fix when you feel it
is ready!

-Matt
Matthew Dillon 
[EMAIL PROTECTED]


Re: DragonFlyBSD 2.0 RELEASE SCHEDULE - Release will be on 20 July 2008

2008-07-11 Thread Jeremy C. Reed
On Fri, 11 Jul 2008, Matthew Dillon wrote:

 HEAD is fine.  We don't branch until Sunday.
 
 I'll leave it in your court then, please commit the fix when you 
 feel it
 is ready!

Okay, it is committed.

I have tested the patch on DragonFly, but this patch to 9.3.4 has had 
little testing.

Please test HEAD's named. See the commit message for details.