[yocto] Yocto Project Status WW39

2016-09-23 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M4

Next Deadline: YP 2.2 M4 which will be Oct. 3rd (5:00pm GMT)


SWAT team rotation: Maxin -> Joshua

https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

*The M3rc1 QA report is out and likely to be released. There were a 
number of bugs, particularly in and around the recent runqemu changes but we 
plan to address these and pretest them before the first M4 rc build.

*We're making good progress with bug fixing and there are some good 
fixes and tweaks going into master. There are also some problems we're seeing 
with build artefacts, particularly with buildtools and uninative which are 
preventing a new uninative release (after the patchelf upgrade).

*Our final release is also dependent on the 4.8 kernel release.

*We have merged various krogoth patches (thanks Armin!). The test 
builds still did show some issues, particularly as the autobuilder has 
increased test coverage but I think we've worked through several of them.

*The defect tracking metric did rise slightly this week from bugs from 
the M3 QA process.


Key YP 2.2 Dates:

*YP 2.2 M4 cut off would be: 10/3/16

*YP 2.2 M4 release would be: 10/28/16


Tracking Metrics:

WDD 2557 (last week 2531)

(https://wiki.yoctoproject.org/charts/combo.html)


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.2_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.2_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.2_Features

[If anyone has suggestions for other information you'd like to see on this 
weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
*   Work Telephone:(503) 712-0534
*Cell:   (208) 244-4460
* Email:stephen.k.jol...@intel.com

-- 
___
yocto mailing list
yocto@yoctoproject.org
https://lists.yoctoproject.org/listinfo/yocto


[yocto] Yocto Project Status WW39

2015-09-25 Thread Jolley, Stephen K
Current Dev Position: YP 2.0 Final
Next Deadline: 2.0 Cut off: Sept. 28, 2015 noon GMT

SWAT team rotation: Paul -> Ross
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team

Key Status/Updates:

  *   'Random' build failures are continuing to cause issues, we're continuing 
to try and tackle them
  *   The Milestone 3 build will be released. There were issues but none 
serious enough to block its release, choosing to concentrate on the final rcs 
now.
  *   Tracked down the cause of the pixbuf bug, unfortunately the fix caused 
other regressions, still working on this
  *   There are several multilib issues being worked on
  *   Prelink also appears broken in several cases, patches are in progress
  *   Biggest threat to release are the 'random' systemd issues and the 
'random' qemuarm and qemux86 segfaults
  *   Reminder:
 *   We have renamed YP 1.9 to YP 2.0.
 *   The current version that is in development will launch as YP 2.0 in 
October, 2015.
 *   The release name for YP 2.0 is 'jethro'.

Key YP 1.9/2.0 Dates:
YP 2.0 Final - 2.0 Cut off: Sept. 28, 2015 noon GMT
YP 2.0 final Release Target: Before Oct. 30, 2015

Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v1.9_Status
https://wiki.yoctoproject.org/wiki/Yocto_1.9_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_1.9_Features

Tracking Metrics:
WDD 2165 (last week 2151 )
(https://wiki.yoctoproject.org/charts/combo.html)

[If anyone has suggestions for other information you'd like to see on this 
weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
*   Work Telephone:  (503) 712-0534
*Cell:(208) 244-4460
* Email: stephen.k.jol...@intel.com

-- 
___
yocto mailing list
yocto@yoctoproject.org
https://lists.yoctoproject.org/listinfo/yocto