HI Noggers,
Has anyone seen this scheduled maintenance notification happening next week?
They maybe upgrading feeds or boards throughout the datacentre - has everyone
seen this notification of works?
It appears to be happening starting 5PM through to 2AM AEST for all Datahalls
on the same date.
]
Sent: Wednesday, 9 August 2017 2:39 PM
To: ; Shaun McGuane
Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th
August
It says 7am -> 4pm in what you quoted? (UTC+10 is AEST)
On Wed, 9 Aug 2017 at 2:36 pm, Shaun McGuane
mailto:sh...@rackcentral.com>> wrote:
H
ppening on the same day at the same time?
On 9/08/2017 2:55 PM, Shaun McGuane wrote:
HI Damien,
My apologies that’s correct – but isn’t anyone concerned about the works being
completed during business hours?
What about increased loading of the active rail once one of them is switched
of
ose eye on things)
Nathan.
On Wed, Aug 9, 2017 at 3:43 PM, Shaun McGuane
mailto:sh...@rackcentral.com>> wrote:
Here is the entire scheduled maintenance windows for all the halls we occupy.
DataHall 2
A Feed - Tuesday 8th August 2017 07:00 UTC +10 until 16:00 UTC +10.
B Feed - Tuesda
nd it would be good
To understand if something is not being done that other providers are legally
bound to do.
Kind Regards
Shaun McGuane
From: AusNOG [mailto:ausnog-boun...@lists.ausnog.net] On Behalf Of Jared Hirst
Sent: Friday, 11 August 2017 10:17 AM
To: Mark Newton ; Nathan Brookfield
Cc: a
work space and you deem this an OH&S high risk?
The law component is the actual testing and not the outage itself.
Kind Regards
Shaun McGuane
From: Simon Cooper [mailto:simon.coo...@nextdc.com]
Sent: Friday, 11 August 2017 11:14 PM
To: Shaun McGuane
Cc: ausnog@lists.ausnog.net
Subject: RE: