Yes. You are right.
On Tue, Nov 13, 2018 at 7:32 AM DImuthu Upeksha
wrote:
> Hi Junkai,
>
> Thanks a lot. I'll try with expiry time then. Is this[1] the place where
> Helix has implemented this logic? If that so, default expiry time should be
> 24 hours. Am I right?
>
> [1]
>
>
1 and 2 are correct. 3 is wrong. The expiry time start counting only when
the workflow is completed. If it is not scheduled ( dont have enought
resource) or still running, Helix never deletes it.
On Sun, Nov 11, 2018 at 8:01 PM DImuthu Upeksha
wrote:
> Hi Junkai,
>
> Thanks for the
Hi Dimuthu,
Couple things here:
1. Only JobQueue in Helix is single branch DAG and 1 job running at a time
with defining parallel job number to be 1. Otherwise, you may see many jobs
running at same time as you set parallel job number to be a different
number. For generic workflow, all jobs
Hi Junkai,
Thanks for the clarification. There are few special properties in our
workflows. All the workflows are single branch DAGs so there will be only
one job running at a time. By looking at the log, I could see that only the
task with this error has been failed. Cleanup agent deleted this
It is possible. For example, if other jobs caused the workflow failed, it
will trigger the monitoring to clean up the workflow. Then if this job is
still running, you may see the problem. That's what I am trying to ask for,
extra thread deleting/cleaning workflows.
I can understand it clean up
Hi Junkai,
There is a cleanup agent [1] who is monitoring currently available
workflows and deleting completed and failed workflows to clear up zookeeper
storage. Do you think that this will be causing this issue?
[1]
Hi Junkai,
There is no manual workflow killing logic implemented but as you have
suggested, I need to verify that. Unfortunately all the helix log levels in
our servers were set to WARN as helix is printing a whole lot of logs in
INFO level so there is no much valuable information in logs. Can
Hmm, that's very strange. The user content store znode only has been
deleted when the workflow is gone. From the log, it shows the znode is
gone. Could you please try to dig the log to find whether the workflow has
been manually killed? If that's the case, then it is possible you have the
problem.
Hi Junkai,
Thanks for your suggestion. You have captured most of the parts correctly.
There are two jobs as job1 and job2. And there is a dependency that job2
depends on job1. Until job1 is completed job2 should not be scheduled. And
task 1 in job 1 is calling that method and it is not updating
In my understanding, it could be you have job1 and job2. The task running
in job1 tries to update content for job2. Then, there could be a race
condition happening here that job2 is not scheduled.
If that's the case, I suggest you can put key-value store at workflow level
since this is cross-job
Hi Junkai,
This method is being called inside a running task. And it is working for
most of the time. I only saw this in 2 occasions for last few months and
both of them happened today and yesterday.
Thanks
Dimuthu
On Fri, Nov 9, 2018 at 2:40 PM Xue Junkai wrote:
> User content store node
User content store node will be created one the job has been scheduled. In
your case, I think the job is not scheduled. This method usually has been
utilized in running task.
Best,
Junkai
On Fri, Nov 9, 2018 at 8:19 AM DImuthu Upeksha
wrote:
> Hi Helix Folks,
>
> I'm having this sporadic
Hi Helix Folks,
I'm having this sporadic issue in some tasks of our workflows when we try
to store a value in the workflow context and I have added both code section
and error message below. Do you have an idea what's causing this? Please
let me know if you need further information. We are using
13 matches