Re: [QA][Test Report] Weekly Status Update as of 20140804

2014-08-05 Thread Shenfeng Liu
Yu Zhen,
  Thanks very much for the update!
  I have run some test cases against RC1 on Win8, and updated the result in
testlink. So far every thing is good.

- Simon



2014-08-05 13:40 GMT+08:00 Yuzhen Fan fanyuz...@gmail.com:

 Hi All,

 We started doing the AOO 4.1.1 Full Path Regression Test(FPR) on June 25,
 and will close it before Aug 8. here is the bi-weekly update (7/21 - 8/4):

 *Test execution:*
 1. We have assigned 176 text executions to about 20 volunteers, and
 completed about 63.6% in execution (112 test executions done). We are
 behind schedule to finish feature FVT before Aug 8. The planned completion
 is 84.8% as of Aug 4

 2. From below test results distributed among platforms, we need to speed up
 the testing on Redhat Linux 64bit(because completed percentage is 46.67%
 which is lower than the average 63.6%) and Mac(made progress on Mac)


 Test CategoryTotalNot RunPassedFailedBlocked
 Completed [%]
 AOO Calc5318312266.04
 Fidelity5310140.00
 AOO Impress6827338060.29
 AOO Writer5016322068.00
 Total176649712363.60


 PlatformTotalNot RunPassedFailedBlockedCompleted
 [%]
 MacOS X3218104043.75
 Redhat Linux 32bit12381075.00
 Redhat Linux 64bit4524165046.67
 Ubuntu Linux 64bit181131394.44
 Windows 7367290080.56
 Windows 8176101064.71
 Windows Server 2012165110068.75
 Total176649712363.60

 *Defect summary:*
 1. We have verified 55 of 4.1.1 resolved showstopper bugs (Total 73 as of
 Aug 4, increased 22 since July 20. Backlog is 18 for all bugs)

 https://issues.apache.org/ooo/buglist.cgi?cmdtype=doremlist_id=153261namedcmd=4.1.1_release_blocker%2B%3Fremaction=runsharer_id=249089

 *Issues  quality highlight:*
 1. We have made big progress these two weeks to verify total 55 defects! We
 still need more defect verification volunteers, to verify language bugs
 2. We(test cases assignees) need speed up testing on Mac  Redhat Linux
 64bitMac(made progress on Mac)

 *Volunteer status: *
 1. We have total 20 test execution volunteers joined in FPR execution work
 since June 24, 2 are from Apache OpenOffice Forum
 2. We have total 16 defect verification volunteers joined in 4.1.1 resolved
 showstopper bug verification work since June 23, 11 new joined these 2
 weeks!

 *Plan for next week:*
 1. Continue to do FPR test with RC1 and bug verification
 2. Remind some test execution volunteers to complete their assignments
 3. Continue to organize the FPR test and bug verification

 Thank you all for effort provided last week, we need your continuous help
 to catch up,  especially on Mac/Linux Redhat!

 Regards,
 Yu Zhen



[QA][Test Report] Weekly Status Update as of 20140804

2014-08-04 Thread Yuzhen Fan
Hi All,

We started doing the AOO 4.1.1 Full Path Regression Test(FPR) on June 25,
and will close it before Aug 8. here is the bi-weekly update (7/21 - 8/4):

*Test execution:*
1. We have assigned 176 text executions to about 20 volunteers, and
completed about 63.6% in execution (112 test executions done). We are
behind schedule to finish feature FVT before Aug 8. The planned completion
is 84.8% as of Aug 4

2. From below test results distributed among platforms, we need to speed up
the testing on Redhat Linux 64bit(because completed percentage is 46.67%
which is lower than the average 63.6%) and Mac(made progress on Mac)


Test CategoryTotalNot RunPassedFailedBlocked
Completed [%]
AOO Calc5318312266.04
Fidelity5310140.00
AOO Impress6827338060.29
AOO Writer5016322068.00
Total176649712363.60


PlatformTotalNot RunPassedFailedBlockedCompleted
[%]
MacOS X3218104043.75
Redhat Linux 32bit12381075.00
Redhat Linux 64bit4524165046.67
Ubuntu Linux 64bit181131394.44
Windows 7367290080.56
Windows 8176101064.71
Windows Server 2012165110068.75
Total176649712363.60

*Defect summary:*
1. We have verified 55 of 4.1.1 resolved showstopper bugs (Total 73 as of
Aug 4, increased 22 since July 20. Backlog is 18 for all bugs)
https://issues.apache.org/ooo/buglist.cgi?cmdtype=doremlist_id=153261namedcmd=4.1.1_release_blocker%2B%3Fremaction=runsharer_id=249089

*Issues  quality highlight:*
1. We have made big progress these two weeks to verify total 55 defects! We
still need more defect verification volunteers, to verify language bugs
2. We(test cases assignees) need speed up testing on Mac  Redhat Linux
64bitMac(made progress on Mac)

*Volunteer status: *
1. We have total 20 test execution volunteers joined in FPR execution work
since June 24, 2 are from Apache OpenOffice Forum
2. We have total 16 defect verification volunteers joined in 4.1.1 resolved
showstopper bug verification work since June 23, 11 new joined these 2
weeks!

*Plan for next week:*
1. Continue to do FPR test with RC1 and bug verification
2. Remind some test execution volunteers to complete their assignments
3. Continue to organize the FPR test and bug verification

Thank you all for effort provided last week, we need your continuous help
to catch up,  especially on Mac/Linux Redhat!

Regards,
Yu Zhen