Re: [Discuss] OpenProject Work Packages Workflow

2016-02-10 Thread Bryan Richter
On Sat, Feb 06, 2016 at 06:38:24AM -0600, Jason Harrer wrote: > > 1) Changing the Milestone work package type is indeed an option. > The reason I chose to create the separate one is because a Milestone > in OP is intended to be kind of like a tag is in git: It marks a > certain point in time. On

Re: [Discuss] OpenProject Work Packages Workflow

2016-02-10 Thread Stephen Yeung
Hi All, Sorry if I'm missing context since I'm new and just starting to read the discussion. I'm a product manager and I can help with some of the terminology.Caveat: Terms are generally flexible, so go with whatever works. Regarding Milestones they're generally meant for big events (i.e. launch