Re: [O] [bug?] Computations on efforts expressed in days

2012-05-02 Thread Sebastien Vauban
Hi Bastien, Bastien wrote: Sebastien Vauban writes: I want to compute efforts given in days. As explained by the doc of `org-effort-durations', we must add a =d= modifier to tell Org that given numbers must be multiplied by 480 (in the case of hours) to get the correct number of

Re: [O] [bug?] Computations on efforts expressed in days

2012-05-01 Thread Bastien
Sebastien Vauban wxhgmqzgwmuf-genee64ty+gs+fvcfc7...@public.gmane.org writes: I want to compute efforts given in days. As explained by the doc of `org-effort-durations', we must add a =d= modifier to tell Org that given numbers must be multiplied by 480 (in the case of hours) to get the

[O] [bug?] Computations on efforts expressed in days

2012-04-17 Thread Sebastien Vauban
Hello, I want to compute efforts given in days. As explained by the doc of `org-effort-durations', we must add a =d= modifier to tell Org that given numbers must be multiplied by 480 (in the case of hours) to get the correct number of corresponding minutes. I did that, but (as shown in the