Re: [O] Repeating tasks with scheduled time

2016-10-05 Thread Nicolas Goaziou
Arkady Grudzinsky writes: > Thanks. I have 8.2 installed. Do you know when 9.0 will be > released? Within 2 weeks, probably. Regards,

Re: [O] Repeating tasks with scheduled time

2016-10-05 Thread Arkady Grudzinsky
On Wed, Oct 05 2016, Nicolas Goaziou wrote: > Hello, > > Arkady Grudzinsky writes: > >> On Tue, Oct 04 2016, Arkady Grudzinsky wrote: >> >>> Say, I have this TODO item which needs to be repeated every >>> evening after 20:00 and if it is not marked as DONE for several >>>

Re: [O] Repeating tasks with scheduled time

2016-10-05 Thread Nicolas Goaziou
Hello, Arkady Grudzinsky writes: > On Tue, Oct 04 2016, Arkady Grudzinsky wrote: > >> Say, I have this TODO item which needs to be repeated every >> evening after 20:00 and if it is not marked as DONE for several >> days, I want it to be moved to the NEAREST 20:00 in the

Re: [O] Repeating tasks with scheduled time

2016-10-04 Thread Arkady Grudzinsky
On Tue, Oct 04 2016, Arkady Grudzinsky wrote: > Say, I have this TODO item which needs to be repeated every > evening after 20:00 and if it is not marked as DONE for several > days, I want it to be moved to the NEAREST 20:00 in the future, > i.e. to 20:00 TODAY if I mark it at noon. I thought,

[O] Repeating tasks with scheduled time

2016-10-04 Thread Arkady Grudzinsky
Say, I have this TODO item which needs to be repeated every evening after 20:00 and if it is not marked as DONE for several days, I want it to be moved to the NEAREST 20:00 in the future, i.e. to 20:00 TODAY if I mark it at noon. I thought, this would accomplish the goal: * TODO Load and run

[O] Repeating tasks

2013-04-29 Thread Marvin Doyley
Hi there, Does anybody knows how to setup org to schedule repeated task between a specified range of dates. For example, suppose I plan to work on a grant proposal between 10 am - 1 pm every other day from May 1 to June 1, how would I do this ? My current practice is specify the start date with

Re: [O] Repeating tasks

2013-04-29 Thread Alexander Baier
Hi Marvin, Marvin Doyley marvin...@gmail.com writes: Hi there, Does anybody knows how to setup org to schedule repeated task between a specified range of dates. For example, suppose I plan to work on a grant proposal between 10 am - 1 pm every other day from May 1 to June 1, how would I do

Re: [O] Repeating tasks

2013-04-29 Thread Marvin Doyley
org-habit is not what I am looking for. I would like to do something like * TODO write proposal Scheduled:2013-04-30 Tue 13:00-15:00 --2013-06-02 Mon +2d The idea is to repeat this task every other day from 2013-04-30 to 2013-06-02 (from 13:30 to 15:00) cheers M

Re: [O] Repeating tasks

2013-04-29 Thread Alexander Baier
Hi Marvin, Marvin Doyley m.doy...@rochester.edu writes: org-habit is not what I am looking for. I would like to do something like * TODO write proposal Scheduled:2013-04-30 Tue 13:00-15:00 --2013-06-02 Mon +2d The idea is to repeat this task every other day from 2013-04-30 to 2013-06-02

Re: [O] Repeating tasks

2013-04-29 Thread Marvin Doyley
Thanks, this is exactly what I was looking for cheers M I will give it a try cheers M On Apr 29, 2013, at 3:56 PM, Alexander Baier lexi.ba...@gmail.com wrote: Hi Marvin, Marvin Doyley m.doy...@rochester.edu writes: org-habit is not what I am looking for. I would like to do something