RE: Questions about EN61000-4-6

2000-03-28 Thread Brian Kunde

Hi Barry,

I commend you on the in-dept study you do when looking at standards, but as
Abraham Lincoln said, If you look for the bad ... you will surely find it.

Standards are written for the majority of products, not for every product in
every environment. That's why there is the TCF rout to compliance.  Remember
that we are ultimately not striving for compliance to standards, but to the
EU Directives which does not give boundaries.

It is impossible to write a standard that some what if wouldn't kill. So
don't expect it to. But, don't think that because a test standard sets some
boundaries that that's all there is to it. If you (your company) designs a
product that 'by design' would be susceptible at some condition or frequency
or in some likely environment that is not covered in a test standard you are
still reasonable for its immunity performance per the Directive. Trying to
determine what to test for is why us EMC engineers make the 'big bucks'. If
you miss a problem area don't worry. It will show up at the customer site
and then you can fix it.

We had a product that passed all our immunity tests (even more strict than
what the EU requires) but at one customer site the product would fail every
day at the same time. What we found out was that they had a clock system
that sent a pulse emission on the AC power line for the entire building to
tell the clocks to advance to the hour and stop. Then a second pulse would
tell all the clocks to start back up synchronizing them throughout the
building.  This pulse was unique enough to get past our Immunity tests. Are
we legally required to make our products immune to this and all known
emissions? Does the Directive give us an alternative?  I believe we are
obligated to design our products to be immune to any emission that it would
'Likely' see in the environments it will be used in which is always a moving
target. But, would we burden the entire industry to be immune to a 'Clock
Pluse' emisision that was only found at a few customer sites? Only YOU can
answer that question, not the standards writter.  As technology advances the
environment our products much work in will be different than today. We as
EMC engineers must be ready to do our jobs even when it requires us to go
beyond the published standards.

The people who are involved in writing standards have a difficult task. My
hat goes off to them for their hard work.  My hope is that I didn't offend
anyone with my comments.

Brian



-Original Message-
From: owner-emc-p...@ieee.org [mailto:owner-emc-p...@ieee.org]On Behalf
Of Barry Ma
Sent: Monday, March 27, 2000 6:33 PM
To: EMC-PSTC
Subject: Questions about EN61000-4-6



Hi Group,

Here are some of my questions and thoughts about EN61000-4-6. Any
corrections and comments are greatly appreciated. In discussion of Wisdom
behind all these standards, Richard Nute summarized three points raised by
Martin Rowe. One of them is reasonableness or appropriateness of the
standard. Please allow me to have better understanding of reasonableness
or appropriateness of the EN61000-4-6.

Both EN61000-4-3 (4-3 in short below) and EN61000-4-6 (4-6) verify the
immunity of EUT against induced disturbances caused by incident
electromagnetic fields from 150 KHz to 1 GHz. The chamber test approach used
in 4-3 is not suitable at lower frequencies (150 KHz to 80 MHz), - not in
principle only technically.  That's why we need to perform 4-6 differently
from 4-3. The methodology of 4-6 is to inject conducted disturbance to
cables connected to the EUT by using direct injection or clamp coupling. The
injected cable currents are supposed to be the same as induced by incident
electromagnetic fields in real world.

The methodology of 4-6 also implies that at low frequencies the possible
disturbance directly coupled into the EUT from incident electromagnetic
fields can be ignored in comparison with the disturbance indirectly coupled
to the EUT via attached cables. For many well-shielded EUT that assumption
works because it is difficult for low frequency electromagnetic fields to
directly get into the EUT through apertures (such as slots, seams, and
holes), whose dimensions are small compared to wavelength.  But what if the
EUT has larger openings or only plastic enclosure?

Let's see an extreme example. A component cannot work properly under the
illumination of 2.5 V/m incident field at 50 MHz The component would feel
2.5 V/m field when installed if the EUT is illuminated by 3 V/m incident
field. But the component could work OK if injecting cable current of 3V into
the EUT.

The boundary 80 MHz between 4-3 (80 to 1000 MHz) and 4-6 (0.15 to 80 MHz) is
not always fixed. It may be adjusted depending on different scenario. That
principle is mentioned only in principle. I would like to see a real example
to adjust the boundary between 4-3 and 4-6. Does it make more sense to setup
a transition region, say 50 to 100 MHz, for both 4-3 and 4-6 to overlap?

For the same EUT the test level

RE: Questions about EN61000-4-6

2000-03-28 Thread Wagner, John P (John)

CISPR 24 allows the transition from conducted to radiated immunity anywhere
from 30MHz to 80MHz.. The European implementation, EN55024 does not.  The
4-6, 4-3 boundary is at 80MHz.

The Japanese did extensive testing for equivalence of RF field exposure to
current injection.  They found that above about 10MHz, the coupling falls as
the log of the frequency.  In other words, 3V/m does not equal 3V.  This has
been taken care of in CISPR 24. The test value of 3V was not changed but the
limits were.

John P. Wagner
Lucent Technologies, Bell Labs
11900 N. Pecos St, Room 2F58
Denver CO  80234
email:  johnwag...@lucent.com
phone:  303 538-4241
fax:  303 538-5211

 --
 From: Barry Ma[SMTP:barry...@altavista.com]
 Reply To: Barry Ma
 Sent: Monday, March 27, 2000 4:32 PM
 To:   EMC-PSTC
 Subject:  Questions about EN61000-4-6
 
 
 Hi Group,
 
 Here are some of my questions and thoughts about EN61000-4-6. Any
 corrections and comments are greatly appreciated. In discussion of Wisdom
 behind all these standards, Richard Nute summarized three points raised
 by Martin Rowe. One of them is reasonableness or appropriateness of the
 standard. Please allow me to have better understanding of reasonableness
 or appropriateness of the EN61000-4-6.
 
 Both EN61000-4-3 (4-3 in short below) and EN61000-4-6 (4-6) verify the
 immunity of EUT against induced disturbances caused by incident
 electromagnetic fields from 150 KHz to 1 GHz. The chamber test approach
 used in 4-3 is not suitable at lower frequencies (150 KHz to 80 MHz), -
 not in principle only technically.  That's why we need to perform 4-6
 differently from 4-3. The methodology of 4-6 is to inject conducted
 disturbance to cables connected to the EUT by using direct injection or
 clamp coupling. The injected cable currents are supposed to be the same as
 induced by incident electromagnetic fields in real world. 
 
 The methodology of 4-6 also implies that at low frequencies the possible
 disturbance directly coupled into the EUT from incident electromagnetic
 fields can be ignored in comparison with the disturbance indirectly
 coupled to the EUT via attached cables. For many well-shielded EUT that
 assumption works because it is difficult for low frequency electromagnetic
 fields to directly get into the EUT through apertures (such as slots,
 seams, and holes), whose dimensions are small compared to wavelength.  But
 what if the EUT has larger openings or only plastic enclosure? 
 
 Let's see an extreme example. A component cannot work properly under the
 illumination of 2.5 V/m incident field at 50 MHz The component would feel
 2.5 V/m field when installed if the EUT is illuminated by 3 V/m incident
 field. But the component could work OK if injecting cable current of 3V
 into the EUT.
 
 The boundary 80 MHz between 4-3 (80 to 1000 MHz) and 4-6 (0.15 to 80 MHz)
 is not always fixed. It may be adjusted depending on different scenario.
 That principle is mentioned only in principle. I would like to see a real
 example to adjust the boundary between 4-3 and 4-6. Does it make more
 sense to setup a transition region, say 50 to 100 MHz, for both 4-3 and
 4-6 to overlap?
 
 For the same EUT the test level of 4-3 is 3V/m, and the test level of 4-6
 is 3V (80% AM @ 1KHz). Is there any explanation or verification available
 to show the equivalence (even roughly) between these two levels in
 interferences with the EUT at boundary frequency? 
 
 In real world all attached cables would have induced currents at the same
 time if an incident field illuminates upon the EUT. In 4-6 test procedure,
 however, all cables are injected one by one in turn. On the other hand, in
 Radiated Emission test we have to manipulate the placement of all attached
 cable to maximize the resultant emission from all cables. Is it fair? I
 mean there seems to be a double standard for Radiated Emission and
 Conducted Immunity.
 
 Best Regards,
 Barry Ma
 b...@anritsu.com
 
 
 
 
 For the largest MP3 index on the Web, go to http://mp3.altavista.com
 
 
 
 
 ---
 This message is from the IEEE EMC Society Product Safety
 Technical Committee emc-pstc discussion list.
 
 To cancel your subscription, send mail to:
  majord...@ieee.org
 with the single line:
  unsubscribe emc-pstc
 
 For help, send mail to the list administrators:
  Jim Bacher:  jim_bac...@mail.monarch.com
  Michael Garretson:pstc_ad...@garretson.org
 
 For policy questions, send mail to:
  Richard Nute:   ri...@ieee.org
 
 

---
This message is from the IEEE EMC Society Product Safety
Technical Committee emc-pstc discussion list.

To cancel your subscription, send mail to:
 majord...@ieee.org
with the single line:
 unsubscribe emc-pstc

For help

Questions about EN61000-4-6

2000-03-27 Thread Barry Ma

Hi Group,

Here are some of my questions and thoughts about EN61000-4-6. Any corrections 
and comments are greatly appreciated. In discussion of Wisdom behind all these 
standards, Richard Nute summarized three points raised by Martin Rowe. One of 
them is reasonableness or appropriateness of the standard. Please allow me to 
have better understanding of reasonableness or appropriateness of the 
EN61000-4-6.

Both EN61000-4-3 (4-3 in short below) and EN61000-4-6 (4-6) verify the immunity 
of EUT against induced disturbances caused by incident electromagnetic fields 
from 150 KHz to 1 GHz. The chamber test approach used in 4-3 is not suitable at 
lower frequencies (150 KHz to 80 MHz), - not in principle only technically.  
That's why we need to perform 4-6 differently from 4-3. The methodology of 4-6 
is to inject conducted disturbance to cables connected to the EUT by using 
direct injection or clamp coupling. The injected cable currents are supposed to 
be the same as induced by incident electromagnetic fields in real world. 

The methodology of 4-6 also implies that at low frequencies the possible 
disturbance directly coupled into the EUT from incident electromagnetic fields 
can be ignored in comparison with the disturbance indirectly coupled to the EUT 
via attached cables. For many well-shielded EUT that assumption works because 
it is difficult for low frequency electromagnetic fields to directly get into 
the EUT through apertures (such as slots, seams, and holes), whose dimensions 
are small compared to wavelength.  But what if the EUT has larger openings or 
only plastic enclosure? 

Let's see an extreme example. A component cannot work properly under the 
illumination of 2.5 V/m incident field at 50 MHz The component would feel 2.5 
V/m field when installed if the EUT is illuminated by 3 V/m incident field. But 
the component could work OK if injecting cable current of 3V into the EUT.

The boundary 80 MHz between 4-3 (80 to 1000 MHz) and 4-6 (0.15 to 80 MHz) is 
not always fixed. It may be adjusted depending on different scenario. That 
principle is mentioned only in principle. I would like to see a real example to 
adjust the boundary between 4-3 and 4-6. Does it make more sense to setup a 
transition region, say 50 to 100 MHz, for both 4-3 and 4-6 to overlap?

For the same EUT the test level of 4-3 is 3V/m, and the test level of 4-6 is 3V 
(80% AM @ 1KHz). Is there any explanation or verification available to show the 
equivalence (even roughly) between these two levels in interferences with the 
EUT at boundary frequency? 

In real world all attached cables would have induced currents at the same time 
if an incident field illuminates upon the EUT. In 4-6 test procedure, however, 
all cables are injected one by one in turn. On the other hand, in Radiated 
Emission test we have to manipulate the placement of all attached cable to 
maximize the resultant emission from all cables. Is it fair? I mean there seems 
to be a double standard for Radiated Emission and Conducted Immunity.

Best Regards,
Barry Ma
b...@anritsu.com




For the largest MP3 index on the Web, go to http://mp3.altavista.com




---
This message is from the IEEE EMC Society Product Safety
Technical Committee emc-pstc discussion list.

To cancel your subscription, send mail to:
 majord...@ieee.org
with the single line:
 unsubscribe emc-pstc

For help, send mail to the list administrators:
 Jim Bacher:  jim_bac...@mail.monarch.com
 Michael Garretson:pstc_ad...@garretson.org

For policy questions, send mail to:
 Richard Nute:   ri...@ieee.org