Hi all,
Next week is the milestone week for 4.15 RC2.
Please note the endgame plan for RC2: https://www.eclipse.org/eclipse/development/plans/freeze_plan_4_15.php
RC2
Release candidate containing fixes for the majority of known outstanding defects that we intend to fix for 2020-03 (4.15). At the end of RC2 build, there should not be any open defects tagged 4.15. All fixes submitted must have a project lead or PMC vote on the bug report, and the fix must be reviewed by an additional committer (any committer other than the one who made the fix). A positive review from a project lead or PMC member means implicit approval and no vote is needed on the bug report. Ongoing changes to documentation, tests or examples do not require approval.
Release candidate containing fixes for the majority of known outstanding defects that we intend to fix for 2020-03 (4.15). At the end of RC2 build, there should not be any open defects tagged 4.15. All fixes submitted must have a project lead or PMC vote on the bug report, and the fix must be reviewed by an additional committer (any committer other than the one who made the fix). A positive review from a project lead or PMC member means implicit approval and no vote is needed on the bug report. Ongoing changes to documentation, tests or examples do not require approval.
Monday: Last day of development (and even then, no "big changes"). After Monday 18:00 ET, no feature work or unrelated fixes are allowed -- only regression fixes.
Tuesday: Testing is welcome.
Tuesday: Testing is welcome.
Wednesday: Fix day with a focus on fixing regressions. No unrelated fixes. Review and thoroughly test all commits.
- The last Wednesday build is the release candidate every team signs off on Thursday.
- The last Wednesday build is the release candidate every team signs off on Thursday.
Thursday: 1-day test pass. Sign-off after re-testing, or at least confirming no changes have been made to your component's code since the last time the component was tested well.
Friday: Build is officially declared and made available.
- The master branch stays closed until the milestone is officially released. (That is, it is not enough that your component has signed off.)
- The master branch stays closed until the milestone is officially released. (That is, it is not enough that your component has signed off.)
Thanks & Regards,
Noopur
Noopur