On Feb 11, 2008, at 9:54 AM, Andreas Zeidler wrote:
i'll do another more in depth wrap-up later, but the quick status is
that the only PLIPs left now without any reviews are #212 and #215.
iirc, tom was planning to do #212 today, so if anyone was up to look
into #215 the first round could be completed...
here's and updated and condensed status overview:
plip
reviews planned
#187: Working Out-of-the-box WebDAV raphael
#201: Improve the UberSelectionWidget UI
martijn tom
#202: Support inline validation and editing [...] raphael
#205: Flexibility Associating Portlet Types [...] andi
#207: Allow Custom Portlet Managers andi
#208: Adapter-Based Local Role Lookup andi
#209: Add buildout to Unified Installer
martijn tom
#212: Use jQuery Javascript Library tom
#213: Prepare for better Syndicationandi
#215: Include new KSS
versions ?? tom
#217: Use Adaptation for Workflow Assignmentandi
#218: Increase Restrictions, and Ability to [...] andi
#220: Improve browser layer support andi
#224: CSRF protection framework
raphael andi
i left out the not-submitted PLIPs as well as those that have already
been reviewed at least twice. nevertheless the remaining list is
still quite long, and the deadline is approaching rapidly, so here's
another call to the team:
* tom, you said you would also look at #201, #209, #215 as well
as leftovers. so, can i suggest you pick at least three more, let
us know which and post an updated ETA, please?
* martijn, as i think we'll have to end up with at least 8
reviews each, it would be great if you do one more as well (and let us
know which, too).
* raphael, i know you've already done several reviews, but could
you please try to post your notes asap? in case there are issues, the
authors will need some time to be able to respond to those...
* danny, you said you'd be able to work on your reviews starting
this week. could you please give us an update about which ones that
will be and when you'll finish them as well?
* as i said earlier, i will still look into #224, but won't get
to do so before the flight back on thursday.
so much for the moment — i'll post another summary once everyone has
stated which PLIPs they'll tackle. and again, please do so asap,
we're quickly running out of time!!
cheers,
andi
--
zeidler it consulting - http://zitc.de/ - [EMAIL PROTECTED]
friedelstraße 31 - 12047 berlin - telefon +49 30 25563779
pgp key at http://zitc.de/pgp - http://wwwkeys.de.pgp.net/
plone 3.0.5 released! -- http://plone.org/products/plone
PGP.sig
Description: This is a digitally signed message part
___
Framework-Team mailing list
Framework-Team@lists.plone.org