Hi,
On Tue, Aug 28, 2018 at 6:11 PM Bill Erickson wrote:
> Feature freeze pushed to Sept 4th.
> XUL and Angular merge freeze Sept 7th.
> Bug Squashing Sept 10-14
> Beta Sept 19th (remaining targets pushed back 2 weeks as well).
I am for this revision to the schedule and also agree with Dan
This all sounds good to me.
Kathy
--
Kathy Lussier
Project Coordinator
Massachusetts Library Network Cooperative
(508) 343-0128kluss...@masslnc.org
On Wed, Aug 29, 2018 at 11:19 AM Bill Erickson wrote:
>
> On Tue, Aug 28, 2018 at 7:39 PM Dan Wells wrote:
>
>> Bill, I think this sounds
On Tue, Aug 28, 2018 at 7:39 PM Dan Wells wrote:
> Bill, I think this sounds fine, but would make two possible suggestions.
>
Thanks for the feedback, Dan.
>
> 1) I think we should get some kind of release built before bug-squashing
> week, to be usable for anyone wanting that sort of testing
Hi Mike
Thank you. This is explanation is helpful and clarifies why outputs are not
what I’m expecting them to be.I’m looking to report on specific staff
member actions at specific workstations so I will have to some more testing.
Elizabeth
From: Open-ils-general