[OE-core] QA Test Review meetings request!

2015-03-13 Thread Jolley, Stephen K
All, Richard has suggested I set up a series of meeting to review the current Yocto Project QA testing being done. This is to insure that the experts have had a chance to sync with the QA team so the right tests are being run during our QA runs. I am soliciting who I should invite and what

[OE-core] YP 1.8 Bug Fix Cutoff is coming soon!

2015-03-17 Thread Jolley, Stephen K
All, If you have an open bug targeting YP 1.8. The cutoff for bug fixing for YP 1.8 is coming up on 3/24/2015. Please make your best effort to get your patches submitted to the mailing list before this date. We will be doing our first release candidate right after the 24th and will only f

[OE-core] YP 1.8 Release Survey/Retrospective

2015-04-15 Thread Jolley, Stephen K
All, Yocto Project 1.8 will be releasing this week! YP provides a major release every six months, and as an open source project we are always working to improve our processes. This survey is for the Yocto Project community to provide feedback into the development process. We would greatly a

[OE-core] YP 1.8 Release Survey/Retrospective - REMINDER

2015-04-22 Thread Jolley, Stephen K
All, Yocto Project 1.8 will be releasing this week! YP provides a major release every six months, and as an open source project we are always working to improve our processes. This survey is for the Yocto Project community to provide feedback into the development process. We would greatly a

[OE-core] YP 1.8 Release Survey/Retrospective - REMINDER

2015-04-29 Thread Jolley, Stephen K
All, Yocto Project 1.8 released last week! YP provides a major release every six months, and as an open source project we are always working to improve our processes. This survey is for the Yocto Project community to provide feedback into the development process. We would greatly appreciate

[OE-core] Yocto Project Status WW21

2015-05-22 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 1 (M1) Next Deadline: M1 cut off of June 23rd Key Status/Updates: gcc 5.1 merged as non-default. Main regressions now with older kernels/security flags gstreamer 0.10 moved oe-core -> meta-oe YP 1.8 was released WW17. YP 1.7.2 was released WW20. YP 1.6.3

[OE-core] Yocto Project Technical Team Meeting

2015-05-22 Thread Jolley, Stephen K
:16010101T02 TZOFFSETFROM:-0800 TZOFFSETTO:-0700 RRULE:FREQ=YEARLY;INTERVAL=1;BYDAY=2SU;BYMONTH=3 END:DAYLIGHT END:VTIMEZONE BEGIN:VEVENT ORGANIZER;CN="Jolley, Stephen K":MAILTO:stephen.k.jol...@intel.com ATTENDEE;ROLE=REQ-PARTICIPANT;PARTSTAT=NEEDS-ACTION;RSVP=TRUE;CN=yocto@yoct oproject.org

[OE-core] Yocto Project Technical Team Meeting

2015-05-22 Thread Jolley, Stephen K
All, Due to very few opens and team sharing being brought up during the meeting, we will be moving the Yocto Project Technical Team meeting to once a month, the first Tuesday of each month, at 8am Pacific time. I will start sending a reminder the Friday before the meeting that the following we

[OE-core] Yocto Project Status WW01

2017-01-03 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M2 -> M3 Next Deadline: YP 2.3 M2 by Jan 23, 2017 SWAT team rotation: Maxin -> Joshua https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *M1 is having some QA difficulties due to some kind of bad interaction between the

[OE-core] Yocto Project Status WW01

2017-01-03 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M2 -> M3 Next Deadline: YP 2.3 M2 by Jan 23, 2017 SWAT team rotation: Maxin -> Joshua https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *M1 is having some QA difficulties due to some kind of bad interaction between the

[OE-core] Yocto Project Status WW02

2017-01-09 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M2 -> M3 Next Deadline: YP 2.3 M2 by Jan 23, 2017 SWAT team rotation: Joshua -> Armin https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *The M1 issues proved tricky to debug and potentially meant there were widespread p

[OE-core] Yocto Project Status WW03’17

2017-01-17 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M2 Next Deadline: YP 2.3 M2 by Jan 23, 2017 SWAT team rotation: Armin -> Saul on Jan. 13, 2017. SWAT team rotation: Saul -> Paul on Jan. 20, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: ·The 2.2.1 release has

[OE-core] Yocto Project Status WW04’17

2017-01-23 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M2 Next Deadline: YP 2.3 M2 by Jan 23, 2017 SWAT team rotation: Saul -> Paul on Jan. 20, 2017. SWAT team rotation: Paul -> Ross on Jan. 27, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: ·The 2.2.1 release has

[OE-core] Yocto Project Status WW05’17

2017-01-30 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M3 Next Deadline: YP 2.3 M3 by Feb. 27, 2017 SWAT team rotation: Paul -> Ross on Jan. 27, 2017. SWAT team rotation: Ross -> Leo on Feb. 3, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: ·The recipe specific sys

[OE-core] Yocto Project Status WW06’17

2017-02-06 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M3 Next Deadline: YP 2.3 M3 by Feb. 27, 2017 SWAT team rotation: Ross -> Leo on Feb. 3, 2017. SWAT team rotation: Leo-> Juro on Feb. 10, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: ·The issues encountered in

[OE-core] Yocto Project Status WW07’17

2017-02-13 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M3 Next Deadline: YP 2.3 M3 by Feb. 27, 2017 SWAT team rotation: Leo-> Juro on Feb. 10, 2017. SWAT team rotation: Juro -> Anibal on Feb. 17, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: ·YP 2.3 M2 was rebuilt

[OE-core] Yocto Project Status WW08’17

2017-02-17 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M3 Next Deadline: YP 2.3 M3 by Feb. 27, 2017 *** FEATURE FREEZE for 2.3 in one week *** SWAT team rotation: Juro -> Anibal on Feb. 17, 2017. SWAT team rotation: Anibal -> Todor on Feb. 24, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team K

[OE-core] Yocto Project Status WW47

2015-11-20 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M1 Next Deadline: YP 2.1 M1 Cutoff December 7, 2015 noon GMT SWAT team rotation: Jussi -> Alejandro https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * YP 2.1 Planning is nearing completion. * Patches continuing

[OE-core] Yocto Project Status WW48

2015-11-30 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M1 Next Deadline: YP 2.1 M1 Cutoff December 7, 2015 noon GMT SWAT team rotation: Alejandro -> Maxim https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * Note that M1 is drawing near, time flies! * YP 2.1 Planning

[OE-core] Yocto Project Status WW49

2015-12-04 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M1 Next Deadline: YP 2.1 M1 Cutoff December 7, 2015 noon GMT SWAT team rotation: Maxim -> Beth https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * M1 cutoff is at the start of next week * Patches continuing to merge into mas

[OE-core] Yocto Project Status WW50

2015-12-11 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M2 Next Deadline: YP 2.1 M2 Cutoff (Feature Freeze) date is January 25, 2016 noon GMT SWAT team rotation: Beth -> Saul https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * M1 release has been build and passed to QA *

[OE-core] Yocto Project Status WW51

2015-12-18 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M2 Next Deadline: YP 2.1 M2 Cutoff (Feature Freeze) date is January 25, 2016 noon GMT SWAT team rotation: Saul -> Paul https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Due to the Holidays, the next weekly status report will be sent out Jan. 8th, 2016

[OE-core] Yocto Project Status WW02

2016-01-08 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M2 Next Deadline: YP 2.1 M2 Cutoff (Feature Freeze) date is January 25, 2016 noon GMT SWAT team rotation: Ross -> Cristian https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * Yocto Project M1 has been released. * Worrying n

[OE-core] Yocto Project Status WW03

2016-01-15 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M2 Next Deadline: YP 2.1 M2 Cutoff (Feature Freeze) date is January 25, 2016 noon GMT SWAT team rotation: Cristian -> Randy https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * Due to some people being sick, we're operating at r

[OE-core] Yocto Project Status WW04

2016-01-22 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M2 Next Deadline: YP 2.1 M2 Cutoff (Feature Freeze) date is January 25, 2016 noon GMT SWAT team rotation: Randy -> Benjamin https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * Yocto Project 2.0.1 was successfully built and is d

[OE-core] Yocto Project Status WW38

2016-09-16 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M4 (M3 is in QA) Next Deadline: YP 2.2 M4 which will be Oct. 3rd (5:00pm GMT) SWAT team rotation: Jussi -> Maxin https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *The M3rc1 build built mostly cleanly and is in QA. We ar

[OE-core] Yocto Project Status WW39

2016-09-23 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M4 Next Deadline: YP 2.2 M4 which will be Oct. 3rd (5:00pm GMT) SWAT team rotation: Maxin -> Joshua https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *The M3rc1 QA report is out and likely to be released. There were a n

[OE-core] Yocto Project Status WW40

2016-09-30 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M4 Next Deadline: YP 2.2 M4 which will be Oct. 3rd (5:00pm GMT) SWAT team rotation: Joshua -> Armin https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *We're seeing a lot of good bug fixing on master, we still have quite

[OE-core] Yocto Project Status WW41

2016-10-07 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M4 Next Deadline: YP 2.2 M4 which will be Oct. 3rd (5:00pm GMT) SWAT team rotation: Armin -> Saul https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *The 4.8 kernel was released and we've updated to the release version.

[OE-core] Yocto Project Status WW43

2016-10-21 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M4 Next Deadline: YP 2.2 M4 which was Oct. 3rd (5:00pm GMT) SWAT team rotation: Paul -> Ross https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *Travel for ELC-E did interrupt these status report, apologies for that. Som

[OE-core] Yocto Project Status WW44

2016-10-28 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M1 Next Deadline: YP 2.3 M1 SWAT team rotation: Paul -> Ross https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *The YP 2.2rc4 QA report looked good and we were nearly able to release. *The kernel CVE issue meant

[OE-core] Yocto Project Status WW45

2016-11-04 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M1 Next Deadline: YP 2.3 M1 by Dec. 12, 2016 SWAT team rotation: Ross -> Randy https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *2.2 was released! *Patches are starting to be merged into master *We are

[OE-core] Yocto Project Status WW45 - UPDATED

2016-11-04 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M1 Next Deadline: YP 2.3 M1 by Dec. 12, 2016 SWAT team rotation: Ross -> Randy https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *2.2 was released! *Patches are starting to be merged into master *We are

[OE-core] Yocto Project Status WW46

2016-11-11 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M1 Next Deadline: YP 2.3 M1 by Dec. 12, 2016 SWAT team rotation: Randy -> Leo https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *2.1.2 is in QA. This did not build 100% cleanly, there is a separate email about that. *

[OE-core] Yocto Project Status WW47

2016-11-18 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M1 Next Deadline: YP 2.3 M1 by Dec. 12, 2016 SWAT team rotation: Leo -> Juro https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *2.1.2 QA report is out and likely to be released imminently. *The QA report for 2.1

[OE-core] Yocto Project Status WW49

2016-11-28 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M1 Next Deadline: YP 2.3 M1 by Dec. 12, 2016 SWAT team rotation: Juro -> Anibal https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *We are switching these reports to Monday instead of Friday, at least for the next month

[OE-core] Yocto Project Status WW50

2016-12-05 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M1 Next Deadline: YP 2.3 M1 by Dec. 12, 2016 SWAT team rotation: Anibal -> Tracy https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *We're now coming to the end of the M1 development period with it closing next Monday.

[OE-core] Yocto Project Status WW14

2016-04-01 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M4 (Stabilization only milestone.) Next Deadline: YP 2.1 M3 Target release date is March 18, 2016 (Is late, see status) SWAT team rotation: Beth -> Saul https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *YP 2.1 M3.rc2 i

[OE-core] Yocto Project Status WW15

2016-04-08 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M4 (Stabilization only milestone.) Next Deadline: YP 2.1 Final Release Target: April 29, 2016 SWAT team rotation: Saul -> Paul https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *YP 2.1 M3.rc2 was released *YP 2.

[OE-core] Yocto Project Status WW16

2016-04-15 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M4 (Stabilization only milestone.) Next Deadline: YP 2.1 Final Release Target: April 29, 2016 SWAT team rotation: Paul -> Ross https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *YP 2.1 M4.rc1 is in QA. Issues so far as m

[OE-core] Yocto Project Status WW17

2016-04-22 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M4 (Stabilization only milestone.) Next Deadline: YP 2.1 Final Release Target: April 29, 2016 SWAT team rotation: Ross -> Randy https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *YP 2.1 M4.rc2 is in QA and it is hoped th

[OE-core] Yocto Project Status WW18

2016-04-29 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M1 Next Deadline: YP 2.2 cut off: June 13, 2016 SWAT team rotation: Randy -> Benjamin https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *YP 2.1 M4.rc2 is going to become the final 2.1 release! *WDD started to ri

[OE-core] Yocto Project Status WW19

2016-05-06 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M1 Next Deadline: YP 2.2 cut off: June 13, 2016 SWAT team rotation: Leo -> Juro https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *Patches started to be merged into master for YP 2.2 M1. *Experimentation with py

[OE-core] Yocto Project Status WW20

2016-05-13 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M1 Next Deadline: YP 2.2 cut off: June 13, 2016 SWAT team rotation: Juro -> Anibal https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * The bitbake python3 branch is nearing readiness, the OE-Core branch is not quite at the same

[OE-core] Yocto Project Status WW21

2016-05-20 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M1 Next Deadline: YP 2.2 cut off: June 13, 2016 SWAT team rotation: Anibal -> Tracy https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *Python3 testing is showing much higher success. There remain some small issues in eS

[OE-core] Yocto Project Status WW22

2016-05-27 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M1 Next Deadline: YP 2.2 cut off: June 13, 2016 SWAT team rotation: Tracy -> Alejandro https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *Python3 is nearly ready to merge, 4 oe-selftest issues remain and some toaster is

[OE-core] Yocto Project Status WW23

2016-06-03 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M1 Next Deadline: YP 2.2 cut off: June 13, 2016 SWAT team rotation: Alejandro -> Jussi https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *Python 3 has now merged, BitBake (inc. Toaster) and OE-Core now use python3 inste

[OE-core] Yocto Project Status WW24

2016-06-10 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M1 Next Deadline: YP 2.2 cut off: June 13, 2016 [3 days - Monday!] SWAT team rotation: Jussi -> Maxim https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *We continue to see various python v3 issues however these are on th

[OE-core] Yocto Project Status WW25

2016-06-17 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M1 [still not in QA] Next Deadline: YP 2.2 M2 cut off would be: 7/18/16 SWAT team rotation: Maxin -> Joshua https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *GTK+3 and Sato rework have merged *A rework of taskd

[OE-core] Yocto Project Status WW22

2015-05-29 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 1 (M1) Next Deadline: M1 cut off of June 23rd Key Status/Updates: There is an RFC about removing bitbake's update_data datastore operation being considered on the mailing list. YP 1.6.3 and has been released this week. The 1.6.x series will now move to commun

[OE-core] Yocto Project Status WW23

2015-06-05 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 1 (M1) Next Deadline: M1 cut off of June 23rd SWAT team rotation: Anibal -> Tracy https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: Bitbake's update_data datastore changes now on a bitbake branch after wider testing Improveme

[OE-core] Yocto Project Status WW24

2015-06-12 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 1 (M1) Next Deadline: M1 cut off of June 23rd SWAT team rotation: Tracy -> Alejandro https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: Key feature for removing stale data from TMPDIR merged Key YP 1.9 Dates: M2 Cut off July 2

[OE-core] Yocto Project Status WW25

2015-06-19 Thread Jolley, Stephen K
NOTE: M1 cut off next week Current Dev Position: 1.9 Milestone 1 (M1) Next Deadline: M1 cut off of June 23rd noon GMT SWAT team rotation: Alejandro -> Beth https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: Datastore changes for getVar default expansion op

[OE-core] Yocto Project Status WW26

2015-06-26 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 2 (M2) Next Deadline: M2 cut off of July 27th at noon GMT SWAT team rotation: Beth -> Saul https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: YP 1.9 M1 is in QA - Target for release is before July 10th. https://wiki.yoctoprojec

[OE-core] Yocto Project Status WW27

2015-07-03 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 2 (M2) Next Deadline: M2 cut off of July 27th at noon GMT SWAT team rotation: Saul -> Paul https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: Fido updated successfully with gcc 5 fixes and other updates (thanks Joshua/Ross) Se

[OE-core] Yocto Project Status WW28

2015-07-10 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 2 (M2) Next Deadline: M2 cut off of July 27th at noon GMT SWAT team rotation: Paul -> Ross https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * Too many issues in 1.9M1 RC1 to release, moving to RC2. * 1.9 M1 RC2 due t

[OE-core] Yocto Project Status WW29

2015-07-17 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 2 (M2) Next Deadline: M2 cut off of July 27th at noon GMT SWAT team rotation: Ross -> Cristian https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * RC2 is out of QA. The full test report can be accessed here

[OE-core] Yocto Project Status WW30

2015-07-24 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 2 (M2) Next Deadline: M2 cut off of July 27th at noon GMT SWAT team rotation: Cristian -> Randy https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * YP 1.9 M2 rc2 is out of QA and will be released shortly. The full test

[OE-core] Yocto Project Status WW31

2015-07-31 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 2 (M2) Next Deadline: M2 cut off of July 27th at noon GMT (on hold, see status) SWAT team rotation: Benjamin -> Juro https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * YP 1.9 M2 has been delayed whilst we investigated au

[OE-core] Yocto Project Status WW32

2015-08-07 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 3 (M3) Next Deadline: M3 cut off of August 24th at noon GMT (on hold, see status) SWAT team rotation: Juro -> Anibal https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * 1.9M2 is in QA, tests so far have shown some

[OE-core] Yocto Project Status WW33

2015-08-14 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 3 (M3) Next Deadline: M3 cut off of August 24th at noon GMT SWAT team rotation: Anibal -> Tracy https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * Its near enough decided that "1.9" will henceforth become the "2.0" rele

[OE-core] Yocto Project Status WW34

2015-08-21 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 3 (M3) Next Deadline: M3 cut off of August 24th at noon GMT SWAT team rotation: Tracy -> Alejandro https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * The autobuilder situation has become problematic as it appears some t

[OE-core] Yocto Project Status WW35

2015-08-28 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 3 (M3) Next Deadline: M3 cut off of August 24th at noon GMT (On hold until most likely late next week) SWAT team rotation: Alejandro -> Jussi https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * Reminder: The current vers

[OE-core] Yocto Project Status WW36

2015-09-04 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 3 (M3) Next Deadline: M3 cut off of August 24th at noon GMT (On hold until most likely late next week) SWAT team rotation: Jussi -> Beth https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * M3/Feature freeze is still bein

[OE-core] Yocto Project Status WW37

2015-09-11 Thread Jolley, Stephen K
Current Dev Position: 1.9 Milestone 3 (M3) Next Deadline: M3 cut off of August 24th at noon GMT (On hold until most likely next week) SWAT team rotation: Beth -> Saul https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * M3/Feature freeze is still be

[OE-core] Yocto Project Status WW38

2015-09-18 Thread Jolley, Stephen K
Current Dev Position: YP 2.0 Final Next Deadline: 2.0 Cut off: Sept. 28, 2015 noon GMT SWAT team rotation: Saul -> Paul https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * The Milestone M3 release is now undergoing QA * The M3 build was not clean, there

[OE-core] Yocto Project Status WW39

2015-09-25 Thread Jolley, Stephen K
Current Dev Position: YP 2.0 Final Next Deadline: 2.0 Cut off: Sept. 28, 2015 noon GMT SWAT team rotation: Paul -> Ross https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * 'Random' build failures are continuing to cause issues, we're continuing to try and

[OE-core] Yocto Project Status WW40

2015-10-02 Thread Jolley, Stephen K
Current Dev Position: YP 2.0 Final (rc1 build in QA) Next Deadline: YP 2.0 Final Release Target: Before Oct. 30, 2015 SWAT team rotation: Ross -> Cristian https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * Two failures were encountered during the rc1 build

[OE-core] Yocto Project Status WW41

2015-10-09 Thread Jolley, Stephen K
Current Dev Position: YP 2.0 Final (rc1 out of QA and being reviewed.) Next Deadline: YP 2.0 Final Release Target: Before Oct. 30, 2015 SWAT team rotation: Cristian -> Randy https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Top Bugs to be tackled: * systemd timeouts in

[OE-core] Yocto Project Status WW41 - Updated

2015-10-09 Thread Jolley, Stephen K
Current Dev Position: YP 2.0 Final (rc1 out of QA and being reviewed.) Next Deadline: YP 2.0 Final Release Target: Before Oct. 30, 2015 SWAT team rotation: Cristian -> Randy https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Top Bugs to be tackled (2.0 release blockers): *

[OE-core] Yocto Project Status WW42

2015-10-16 Thread Jolley, Stephen K
Current Dev Position: YP 2.0 Final (rc2 to be built soon) Next Deadline: YP 2.0 Final Release Target: Before Oct. 30, 2015 SWAT team rotation: Randy -> Benjamin https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Top Bugs to be tackled (2.0 release blockers): * systemd t

[OE-core] Yocto Project Status WW43

2015-10-23 Thread Jolley, Stephen K
Current Dev Position: YP 2.0 Final (rc2 is in QA) Next Deadline: YP 2.0 Final Release Target: Oct. 30, 2015 (We will miss this date.) SWAT team rotation: Benjamin -> Juro https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Top Bugs to be tackled (2.0 release blockers): * system

[OE-core] Yocto Project Status WW44

2015-10-30 Thread Jolley, Stephen K
Current Dev Position: YP 2.0 Final (preparing rc3) Next Deadline: YP 2.0 Final Release Target: Oct. 30, 2015 (We are targeting Nov. 6th) SWAT team rotation: Juro -> Anibal https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Top Bugs to be tackled (2.0 release blockers): *

[OE-core] Yocto Project Status WW45

2015-11-06 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 Planning Next Deadline: YP 2.1 M1 Cutoff December 7, 2015 noon GMT SWAT team rotation: Anibal -> Tracy https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * We have approved YP 1.7.3 rc1 for release, it should release shor

[OE-core] Yocto Project Status WW46

2015-11-13 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 Planning Next Deadline: YP 2.1 M1 Cutoff December 7, 2015 noon GMT SWAT team rotation: Tracy -> Alejandro https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * 2.0 was released! * Undergoing planning for 2.1 * Have various

[OE-core] Yocto Project Status WW05

2016-01-29 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M3 Next Deadline: YP 2.1 M2 Target release date is February 12, 2016 SWAT team rotation: Benjamin -> Alejandro Franco https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * Due to the number of open bugs against Yocto Project 2.0.1

[OE-core] Yocto Project Status WW05

2016-01-29 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M3 Next Deadline: YP 2.1 M2 Target release date is February 12, 2016 SWAT team rotation: Benjamin -> Alejandro Franco https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * Due to the number of open bugs against Yocto Project 2.0.1

[OE-core] Yocto Project Status WW06

2016-02-05 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M3 Next Deadline: YP 2.1 M2 Target release date is February 12, 2016 SWAT team rotation: Alejandro Franco -> Juro https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * YP 2.1 M2-rc1 QA report has been published. The number of High

[OE-core] Yocto Project Status WW07

2016-02-12 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M3 Next Deadline: YP 2.1 M2 Target release date is February 12, 2016 (Will slip a few weeks.) SWAT team rotation: Juro -> Anibal https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: * We merged a change to python function variable

[OE-core] Yocto Project Status WW08

2016-02-19 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M3 Next Deadline: YP 2.1 M2 Target release date is February 12, 2016 (Will slip a few weeks.) SWAT team rotation: Anibal -> Tracy https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *A build for M2-rc3 was passed to QA af

[OE-core] Yocto Project Status WW10

2016-03-04 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M4 (Stabilization only milestone.) Next Deadline: YP 2.1 M3 Target release date is March 18, 2016 SWAT team rotation: Alejandro -> Jussi https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *M3 is proving a challenge to s

[OE-core] Yocto Project Status WW11

2016-03-11 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M4 (Stabilization only milestone.) Next Deadline: YP 2.1 M3 Target release date is March 18, 2016 (Will be late, see status) SWAT team rotation: Jussi -> Maxin https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *The good

[OE-core] Yocto Project Status WW12

2016-03-19 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M4 (Stabilization only milestone.) Next Deadline: YP 2.1 M3 Target release date is March 18, 2016 (Will be late, see status) SWAT team rotation: Maxin -> Joshua https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *The M3

[OE-core] Yocto Project Status WW13

2016-03-25 Thread Jolley, Stephen K
Current Dev Position: YP 2.1 M4 (Stabilization only milestone.) Next Deadline: YP 2.1 M3 Target release date is March 18, 2016 (Is late, see status) SWAT team rotation: Joshua -> Beth https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *YP 2.1 M3 rc1

[OE-core] Yocto Project Status WW09’17

2017-02-27 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M3 Next Deadline: YP 2.3 M3 by Feb. 27, 2017 *** FEATURE FREEZE for 2.3 is now in effect. *** SWAT team rotation: Anibal -> Todor on Feb. 24, 2017. SWAT team rotation: Todor -> Tracy on Mar. 4, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Tea

[OE-core] Yocto Project Status WW10’17

2017-03-06 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M3 Next Deadline: YP 2.3 M3 by Feb. 27, 2017 *** FEATURE FREEZE for 2.3 is now in effect. *** SWAT team rotation: Todor -> Tracy on Mar. 4, 2017. SWAT team rotation: Tracy -> Alejandro on Mar. 11, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_

[OE-core] Yocto Project Status WW11’17

2017-03-13 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M3 Next Deadline: YP 2.3 M3 by Feb. 27, 2017 *** FEATURE FREEZE for 2.3 is now in effect. *** SWAT team rotation: Tracy -> Alejandro on Mar. 11, 2017. SWAT team rotation: Alejandro -> Jussi on Mar. 18, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_

[OE-core] Yocto Project Status WW12’17

2017-03-20 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M4 Next Deadline: YP 2.3 M4 Cutoff is April 10, 2017 *** FEATURE FREEZE for 2.3 is now in effect. *** SWAT team rotation: Alejandro -> Jussi on Mar. 17, 2017. SWAT team rotation: Jussi-> Stephano on Mar. 24, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Fa

[OE-core] Yocto Project Status WW13’17

2017-03-27 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M4 Next Deadline: YP 2.3 M4 Cutoff is April 10, 2017 *** FEATURE FREEZE for 2.3 is now in effect. *** SWAT team rotation: Jussi -> Stephano on Mar. 24, 2017. SWAT team rotation: Stephano -> Maxin on Mar. 31, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Fa

[OE-core] Yocto Project Status WW14’17

2017-04-03 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M4 Next Deadline: YP 2.3 M4 Cutoff is April 10, 2017 *** FEATURE FREEZE for 2.3 is now in effect. *** SWAT team rotation: Stephano -> Maxin on Mar. 31, 2017. SWAT team rotation: Maxin -> Cal on April 7, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure

[OE-core] Yocto Project Status WW15’17

2017-04-10 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M4 Next Deadline: YP 2.3 M4 Cutoff is April 10, 2017 *** FEATURE FREEZE for 2.3 is now in effect. *** SWAT team rotation: Maxin -> Cal on April 7, 2017. SWAT team rotation: Cal -> Joshua on April 14, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Sw

[OE-core] Yocto Project Status WW16’17

2017-04-18 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M4 Next Deadline: YP 2.3 M4 Cutoff is April 10, 2017 *** FEATURE FREEZE for 2.3 is now in effect. *** SWAT team rotation: Cal -> Joshua on April 14, 2017. SWAT team rotation: Joshua -> Armin on April 21, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Failur

[OE-core] Yocto Project Status WW17’17

2017-04-24 Thread Jolley, Stephen K
Current Dev Position: YP 2.3 M4 Next Deadline: YP 2.3 M4 Cutoff is April 10, 2017 *** FEATURE FREEZE for 2.3 is now in effect. *** SWAT team rotation: Joshua -> Armin on April 21, 2017. SWAT team rotation: Armin -> Saul on April 28, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Failur

[OE-core] Yocto Project Status WW18’17

2017-05-02 Thread Jolley, Stephen K
Current Dev Position: Planning for YP 2.4 Next Deadline: YP 2.1.3 Cut off May 15, 2017 *** FEATURE FREEZE for 2.3 is now in effect. *** SWAT team rotation: Armin -> Paul on April 28, 2017. SWAT team rotation: Paul -> Ross on April 21, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Fail

[OE-core] Yocto Project Status WW20’17

2017-05-15 Thread Jolley, Stephen K
Current Dev Position: Planning for YP 2.4 Next Deadline: YP 2.1.3 Cut off May 15, 2017 – Still TBD SWAT team rotation: Ross -> Leo on May 12, 2017. SWAT team rotation: Leo -> Juro, on May 19, 2017. https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: ·

[OE-core] Yocto Project Status WW26

2016-06-24 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M2 Next Deadline: YP 2.2 M2 cut off would be: 7/18/16 SWAT team rotation: Joshua -> Armin https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *After delays in addressing several issues, a build of 2.2 M1 went into QA and

[OE-core] Yocto Project Status WW36

2016-09-02 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M3 Stabilizing Next Deadline: YP 2.2 M4 which will be Oct. 3rd (5:00pm GMT) SWAT team rotation: Tracy -> Alejandro https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *M3 is proving to be 'somewhat problematic' in that it'

[OE-core] Yocto Bugzilla category cleanup

2016-09-09 Thread Jolley, Stephen K
All, We are planning to spin up a team to look at redefining/cleaning up the categories in Yocto's bugzilla. We will then work on the migration to these new categories and ensure each category has the correct default owner. If you are interested in being an active participant, please let

[OE-core] Yocto Project Status WW37

2016-09-09 Thread Jolley, Stephen K
Current Dev Position: YP 2.2 M4 (M3 Building rc1) Next Deadline: YP 2.2 M4 which will be Oct. 3rd (5:00pm GMT) SWAT team rotation: Alejandro -> Jussi https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team Key Status/Updates: *M3 has continued to be problematic: o The qem

[OE-core] Yocto Project Unassigned Bugs - Help Needed

2018-12-10 Thread Jolley, Stephen K
All, The triage team meets weekly and does its best to handle the bugs reported into the Bugzilla. The number of people attending that meeting has fallen, as have the number of people available to help fix bugs. One of the things we hear users report is they don't know how to help. We (the tr

  1   2   3   >