Planning for M5: June 23, 2014 [RDP2]

2014-05-23 Thread Stephen F Northover

Hi all,

The next milestone M5, June 23, 2014 [RDP2], is an important one. 
Essentially, we are shipping FX for 8u20 after this.  There is a week 
before the final FX ZBB date which is July 1, 2014, but we should not be 
touching any code during this week.  After July 1 ZBB, we are stopping 
all development on FX 8u20 and starting on 8u40.


Here is the plan for M5:

May 26-30: Fix P123, fix or move P45 to 8u40
June 2-5: Fix P123, zero P45 targeted to 8u20
June 9-13: Fix P123, defer bugs that won't make it
June 16-20: Code freeze, ramp down rules, fix doc bugs

During the week June 16-20, the usual milestone rules will be in effect 
and we are likely to be quite ruthless about any code changes.  We will 
likely only accept fixes for P12 critical bugs / regressions.


Thanks to everyone for their hard work,

Steve and Kevin


Re: Planning for M5: June 23, 2014 [RDP2]

2014-05-23 Thread Lisa Selle
Steve can you clarify the process for various stages for retargeting 
bugs to a later release?


On 5/23/2014 1:15 PM, Stephen F Northover wrote:

Hi all,

The next milestone M5, June 23, 2014 [RDP2], is an important one. 
Essentially, we are shipping FX for 8u20 after this.  There is a week 
before the final FX ZBB date which is July 1, 2014, but we should not 
be touching any code during this week.  After July 1 ZBB, we are 
stopping all development on FX 8u20 and starting on 8u40.


Here is the plan for M5:

May 26-30: Fix P123, fix or move P45 to 8u40
June 2-5: Fix P123, zero P45 targeted to 8u20
June 9-13: Fix P123, defer bugs that won't make it
June 16-20: Code freeze, ramp down rules, fix doc bugs

During the week June 16-20, the usual milestone rules will be in 
effect and we are likely to be quite ruthless about any code changes.  
We will likely only accept fixes for P12 critical bugs / regressions.


Thanks to everyone for their hard work,

Steve and Kevin