Hi,

Testperf meeting is coming today!
https://wiki.opnfv.org/display/meetings/Test+Working+Group+Weekly+Meeting

There are 2 topics, i.e., resiliency test threshold and long duration test 
plan, where we are seeking your expert opinions and help. Please join the 
meeting!
I will elaborate on some details in the following to form some common 
foundations first.

1.       Resiliency test threshold

a)         This topic is from https://gerrit.opnfv.org/gerrit/#/c/37715/, where 
a test case to validate the reliable capacity and to form baseline for 
subsequent test is proposed.

b)         SUT need to be able to setting up certain number, i.e., threshold, 
VM pairs under some stressful testing conditions

c)         The methodology/rationales for setting up this threshold need to be 
further determined

2.       Long duration testing

a)         Test community has a proposal regarding long duration test to 
validate the stability and confidence level of our release

                         i.              
https://wiki.opnfv.org/display/testing/Euphrates+Testing

b)         Currently, we have Intel-18 POD granted for the long duration test. 
In the meanwhile, we have received different opinions regarding the SUTs.

c)         What we need here is to confirm the testing arrangement for the time 
being and then make this test plan automatically built on that POD.

                         i.              The test plan will included 
multi-projects following a pre-defined timeline over some suitable SUT.

Thanks in advance!
Gabriel