I am able to power on vms on newly upgraded host, But not able to migrate VMs
from other hosts to new host or newly upgraded hosts to other hosts. This was
worked fine before upgraded.
i see below logs
Unable to read from monitor: Connection reset by peer
internal error: qemu unexpectedly
Hi, I'm pretty stuck at the moment so I hope someone can help me.
I have an oVirt 4.3 data center with two hosts. Recently, I attempted to
segregate migration traffic from the the standard ovirtmgmt network, where
the VM traffic and all other traffic resides.
I set up the VLAN on my router and
I need to migrate running VMs from one host in our cluster to another
however the task keeps failing any time I start a migration. The engine
logs show a few different errors as follows.
2019-07-10 09:53:19,440-04 ERROR
[org.ovirt.engine.core.vdsbroker.monitoring.VmAnalyzer]
Hi,
After upgrade to 4.3.3 from 4.3.2, VM migrations are failing with
"No available host to migrate VMs to"
Interestingly, this happens in one of our clusters, not on the
other. Both on the same datacenter, both in 4.3 compatibility version.
This are the relevant lines from
"Bryan Sockel" writes:
> Thanks for the info, I will be sure to update to 4.2.2 when it is ready.
> With out the ability to migrate vm's based on this image it makes it less
> convenient to patch my servers on a more consistent basis.I was also
> experiencing this
"Bryan Sockel" writes:
> I am having an issue migrating all vm's based on a specific template. The
> template was created in a previous ovirt environment (4.1), and all VM's
> deployed from this template experience the same issue.
>
> I would like to find a
You will need at least 3.5 to import the storage and you should also handle
the consistency if any VMs on the storage are up.
Yaniv Dary
Technical Product Manager
Red Hat Israel Ltd.
34 Jerusalem Road
Building A, 4th floor
Ra'anana, Israel 4350109
Tel : +972 (9) 7692306
8272306
Email:
I have a question regarding migration of VMs. It's my hope that someone
can tell me if my migration idea can work or if it is not possible
I want to migrate about 100-200 VMs from one oVirt deployment to a new
oVirt deployment. Some of the VMs are over 3TB in size. Exporting and
importing
8 matches