Hello everyone,
I'm new on this list and also starting with Netbackup so bare with me :)
As I was trying to understand what goes on when I have a calendar-based
schedule with a window that spans midnight I just found out there are some
issues with this the latest 6.5.2. Please check this
.
From: [EMAIL PROTECTED] [EMAIL PROTECTED] On Behalf Of Jorge Fábregas [EMAIL
PROTECTED]
Sent: Thursday, August 21, 2008 9:06 PM
To: veritas-bu@mailman.eng.auburn.edu
Subject: [Veritas-bu] Calendar Schedules over Midnight 6.5.2 issue
Hello everyone,
I'm new on this list
On Thursday 21 August 2008 09:21:45 pm Clausen, Matt R [EQ] wrote:
The job queues, starts, runs into an issue and re-queues itself except this
time doesn't get to start until after midnight Here is where the
Retries Allowed after Runday checkbox comes in.
Thanks Matt for that wonderful
.
From: [EMAIL PROTECTED] [EMAIL PROTECTED] On Behalf Of Jorge Fábregas [EMAIL
PROTECTED]
Sent: Thursday, August 21, 2008 9:42 PM
To: veritas-bu@mailman.eng.auburn.edu
Subject: Re: [Veritas-bu] Calendar Schedules over Midnight 6.5.2 issue
On Thursday 21 August 2008 09:21:45 pm Clausen
On Thursday 21 August 2008 09:52:40 pm Clausen, Matt R [EQ] wrote:
It terminated because the next day is not a Run day. With a calendar
backup, the checked day(s) denote the run day.
All clear now Matt. Thanks a million!