On Sat, Feb 4, 2012 at 3:23 PM, Tony Graziano
<[email protected]> wrote:
> If there are several different changes, should that table allow the
> admin to combine them for one scheduled change?

They changes would combine automatically, it's how

> On Sat, Feb 4, 2012 at 3:18 PM, Martin Steinmann <[email protected]> wrote:
>> If we have scheduled restarts of components, we will also need a table where
>> we can see what actions are queued and at what time.  What if several
>> changes are made that trigger such action?

Good point! If admin schedules a CDR change and a Proxy then comes in,
it would be too hard to implement have manage multiple scheduled
pending config changes.

The schedule part i think i too fancy to get right the first time.
Strike the schedule, and admin just gets a UI to proceed or cancel and
leaving pending config changes.

> Should the operator be able to
>> roll back or cancel a change before it is activated?

It would be very useful to do this, but we don't have that capability
and it would be difficult i think because postgres data has already
been committed. Not impossible for future revs i think.

> Should the operator be
>> informed after the action was taken about its status?

yes, job status table as before.