Oliver Zeigermann wrote:

To be on the save side, please check if you agree with the following 2.1 release plan:

- Feature freeze: August 1st
- Creation of release branch for full beta->rc->final->maintenance cycle: August 2nd
- Beta1 release: Ausust 10th
- Max. number of beta releases: 2 (with at most 4 weeks between them)
- Max. number of release candidates: 2 (with at most 2 weeks between them)
- Release Manager: Oliver Zeigermann (will be his final Slide release)


Anything missing? Anything you disagree with?


Is there a minimal term between rc/beta releases?

I have some improvements to ACL in the pipeline but I won't have time to commit them before August 1. These include simple code improvements but also enhancements such as the ability to define custom privileges. I guess these won't be able to make it into 2.1 :-(

There is one thing I think MUST be done before the release. I noticed that currently the org.apache.util package is being maintained at two separate places in the CVS! Both in src/util and in webdavclient/clientlib/src/java. Surely this must be consolidated.

Otherwise +1 for the release plan.

--
Unico