The backfill scheduler will get to the end of the queue if it can do so in 30 seconds (or whatever you have backfill_interval configured to be). The sdiag command will report actual scheduler run times. The "cycle" times are in units of microseconds.

Quoting Martins Innus <min...@buffalo.edu>:
Moe,

On 7/7/15 7:04 PM, Moe Jette wrote:


-- Backfill scheduler: The configured backfill_interval value (default 30
   seconds) is now interpreted as a maximum run time for the backfill
   scheduler. Once reached, the scheduler will build a new job queue and
   start over, even if not all jobs have been tested.

I assume with bf_continue enabled we can still get to the end of the queue? Or is that not the case?

Martins


--