On Fri, Nov 15, 2013 at 11:19 PM, Steven Bower <smb-apa...@alcyon.net> wrote:
> So its something that can happen multiple times during the lifetime of
> process, but i'm guessing something not occuring very often?

That's right.

>
> Also is there a way to hook the shutdown of the core?

You can use SolrCore.addCloseHook method.

>
> steve
>
>
> On Fri, Nov 15, 2013 at 12:08 PM, Alan Woodward <a...@flax.co.uk> wrote:
>
>> Hi Steven,
>>
>> It's called when the handler is created, either at SolrCore construction
>> time (solr startup or core reload) or the first time the handler is
>> requested if it's a lazy-loading handler.
>>
>> Alan Woodward
>> www.flax.co.uk
>>
>>
>> On 15 Nov 2013, at 15:40, Steven Bower wrote:
>>
>> > Under what circumstances will a handler that implements SolrCoreAware
>> have
>> > its inform() method called?
>> >
>> > thanks,
>> >
>> > steve
>>
>>



-- 
Regards,
Shalin Shekhar Mangar.