Nile dam set to generate power, Ethiopia to consult Egypt, Sudan ahead
Article
Comments (0)
email Email
print Print
pdfSave
separation
increase
decrease
separation
separation
facebookmyspacetwitterbuzzyahoo
By Tesfa-Alem Tekle
January 20, 2016 (ADDIS ABABA) – An Ethiopian official said Wednesday
that the Grand Renaissance Dam (GERD) which the horn of Africa’s
nation is constructing along the Nile River is due to begin generating
power very soon.
JPEG - 19.2 kb
The planned Grand Ethiopian Renaissance Dam project (AP)
A government official at the Ethiopia Electric and Power Corporation
(EEPCo), who spoke anonymously because he is not authorized to brief
the media, said the mega project is set to start generating 750
megawatts of electricity.
According to the official, the initial electricity generation will
start soon the two turbines which recently arrived at the dam site and
will get installed in the coming weeks. Ethiopia has ordered a total
of 16 turbines from companies oversees which will enable the massive
power plant project to generate 6,000 megawatts of electricity upon
completion.
Concerns are expected to rise from the Egyptian side when the Nile dam
begins generating power.
While Sudan is seen as a beneficiary from the new dam which is at 20km
from the border, Egypt fears that water in the dam’s large reservoir
will be used for irrigation, diminishing downstream supply. But,
Ethiopia insists that the main purpose of this project is to produce
power and water will continue to reach Egypt like before.
Speaking to Sudan Tribune, Girma Fikru, a water resources engineer in
Addis Ababa said Ethiopia’s plan to start generating electricity from
the power plant while tripartite negotiations are yet in progress
might not be a smarter move.
“Ethiopia’s move to start generating power in the middle of the
ongoing tripartite meetings on GERD could risk collapse of the
negotiations and might trigger a renewed dispute over the Nile water
resources,” said Fikru.
He said Ethiopia should first finalize a trust building activities
with lower riparian countries most importantly with Egypt before
starting the dam to generate power.
The Ethiopian official however added Addis Ababa will be engaged in
consultations with lower riparian countries (Egypt and Sudan) to
decide on the amount of water the Dam reservoir should be holding
before it launches its first phase power generation.
The $4.2 billion huge project being constructed by the government and
people of Ethiopia has so far consumed about $2.2 billion.
Debretsion Gebremichael, Deputy Prime Minister for Finance and
Economic Cluster and Minister of Communication and Information
Technology said the government has no financial constraints and
construction of the dam will be completed as per schedule.
Some 4 million cubic meter concrete has so far been poured to the
1,780m long and 145m high dam.
During their tripartite meeting last month, Ethiopia Sudan and Egypt
agreed in Khartoum to speed up the impact assessment study of the
controversial dam project which lower riparian countries particularly
Egypt fears would ultimately curtail its historical water share.
During the meeting, Cairo had asked for an increase to bottom water
outlets at the dam from two to four to prevent significant reduce on
water flow to its territory. Ethiopia however refused Cairo’s request
arguing that enough impact studies had already been made and no
redesigning was necessary.
The three parties have selected two foreign consultancy firms, the
French Artelia and BRL groups to undertake impact studies on the Dam
particularly if there are risks that could bring significant harm on
Sudan and Egypt.
The construction of what would be Africa’s largest and amongst the
world’s top ten leading power plants has been a source of dispute with
Egypt which over 80 % of people depend on for water supply.
Egypt has been taking the project as a threat to its national water
security and has previously considered other options including
military action to halt the dam project.
However Egypt seems to have changed its position lately following
relentless efforts to build mutual trust with the North African
country regarding the grand dam project.
Egypt’s irrigation minister, Hossam Moghazi, on Wednesday said that
although Cairo is concerned about the Ethiopia’s giant dam project,
the country however doesn’t view it as a “threat”.
Moghazi confirmed that Egypt is not against the development of the
Nile Basin countries in deviating from 1929 and 1959 treaties which
had granted the North African nation the right to veto any projects
upstream.
Ethiopia said the project which is being constructed some 25km away
from the Sudanese border is never intended to harm Egyptians but is
necessary for development and should be taken as a symbol of
cooperation among Egypt, Sudan and Ethiopia.
Ethiopian officials stress that the main goal of the dam is “combating
poverty and realizing development and prosperity”
The construction of the ambitious hydroelectric power project on the
African continent has reached at nearly halfway mark and is slated for
completion in 2017.
(ST)
--
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to
[email protected]
Visit this group at https://groups.google.com/d/forum/southsudankob
View this message at
https://groups.google.com/d/msg/southsudankob/topic-id/message-id
For more options, visit https://groups.google.com/d/optout
---
You received this message because you are subscribed to the Google Groups
"South Sudan Info - The Kob" group.
To unsubscribe from this group and stop receiving emails from it, send an email
to [email protected].
To post to this group, send email to [email protected].
Visit this group at https://groups.google.com/group/SouthSudanKob.
To view this discussion on the web visit
https://groups.google.com/d/msgid/SouthSudanKob/CAJb14or2Pfp7siGg5JKntxgfbnefuxA1zHUiPVetgTXGY1%2BTpQ%40mail.gmail.com.
For more options, visit https://groups.google.com/d/optout.