I am working on a retrofit project (church) that is requiring a dry system.
I am looking at the using the room design method for my calcs.  Is there any
reason that this will not work for a dry system?  The only thing I can find
is a line in the annex that says the increases or decreases allowed or
required by 11.2.3.2 do not apply.  This would tend to make one think that
using this in a dry system is acceptable.  

 

What think ye?

 