Did the Cal-Val work OK with the flow from the inspector's test?
At 03:19 PM 1/18/2008, you wrote:
Off Standpipe (in direction of flow):
BV - Cla-Val - Tee (to FDV) - BV - CHV - WFS - T&D (to Spkrs.)
Worked well.
Tom
Tom,
Is the BF before the Cla-Val required or was it installed in case there
is maintenance required on the Cla-Val and not to shut down the feed?