Yes! I looked at the 2012 ROP rejecting your proposal and posted this before
I checked the 2012 ed. of #13. I am not sure how ROP's and ROC's work
exactly. Why would The 2012 ROP page 13-59 still have your 2" gap in there,
and be rejected?  

-----Original Message-----
From: Roland Huggins [mailto:[email protected]] 
Sent: Tuesday, May 22, 2012 11:58 AM
To: [email protected]
Subject: Re: Intent of 8.15.1.2.7

But the 2" air gap was accepted at the ROC (and existed in the 2010 ed  
as part of 8.15.1.2.17)

Roland


On May 17, 2012, at 6:01 AM, Brad Casterline wrote:

> Steve,
>
> Here is a possible twist though regarding the latest ROP (or maybe I  
> have
> not followed through completely): Page 13-59 says ENTIRELY means  
> exactly
> that, so Roland's 2" max gap was rejected. But page 13-86 says the  
> 3000 min.
> operating area for non-sprinklered comb. concealed spaces is not  
> required
> when the space is full of non-comb. insulation with a max 2" gap! Is  
> this
> 'circular reasoning' or my lack of comprehension? Can it be that a
> distinction has to be made between comb. concealed spaces- those  
> that allow
> occupancy above them (floor decks) and those that do not (roof decks)?
>
> Thanks,
> Brad
>
>
>
> _______________________________________________
> Sprinklerforum mailing list
> [email protected]
> http://fireball.firesprinkler.org/mailman/listinfo/sprinklerforum

_______________________________________________
Sprinklerforum mailing list
[email protected]
http://fireball.firesprinkler.org/mailman/listinfo/sprinklerforum

_______________________________________________
Sprinklerforum mailing list
[email protected]
http://fireball.firesprinkler.org/mailman/listinfo/sprinklerforum

Reply via email to