We have a dentist office project that does not have a sprinkler system in it. The plumber has provided us with a 1 rpz to connect 1 head to cover the gas cylinder storage room. Probably 6x2. They came off of a ¾ domestic line. We created a set of plans showing the work but has been rejected. Notes said to provide calcs, show riser diagram and domestic demand. The contractor is telling me they are already over on their domestic demand for the size line they have. Should I use their domestic demand or follow the demand layed out in 13R. Has anybody run across this situation before?
Chris _______________________________________________ Sprinklerforum mailing list [email protected] http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org