John,
See my post to you directly, off list.
Carl
John Watkins wrote:
>
> Carl, I finally got to this "phase." Knowing that you had at one time
> offered to come and do this, I thought the experience would be
> useful, so I set to . . .
>
> The first few seemed to go OK and then I encountered some problems.
> My question is, does it much matter if I go ahead and make some other
> modifications in the meantime -- meaning until you can come help if
> you think it necessary?
>
> As you probably remember, I'm already using FM Pro 5.5 and have, I
> think correctly, updated 1.02 to run with it.
>
> >5) Fixed bug in the way Global Date is formatted in PLEDGES
> >------------------------------------------------------------
> >TO ADD THIS FIX TO YOUR VERSION OF EBASE:
> >--------------------------------------------
> >A) Determine if this is a problem:
> >
> >-Get into ebase using your master password. Once you're on the HOME
> >screen, Click on the Pledges button
> >and them the View pledges button to bring you to the pledges_.102 file.
> >Now select: File->Define->Fields.
> >
> >-Double-click on the field named " Global Date".
> >
> >-The "Specify Calculation" dialog box will appear.
>
> I have no pledges but went to the pledges file anyway. What appeared
> is an Option Box. The field is described as Type: Global and Option:
> Date. I can't get to the specify calculation screen
>
> >The correct
> >calculation
> >for this field is as follows:
> >
> >CONSTANT::gToday
> >
> >-And that the Calculation result is field on the Specify Calculation
> >dialog box is set to "Date"
> >
> >PROBLEMS WITH SLOWDOWNS IN TRANSISTION FROM PAYMENT HISTORY TO PAYMENT
> >-----------------------------------------------------------------------
> >
> >6) Fixed bug causing slowdown in transition from payment history to
> >payment with large data sets
> >
> >TO ADD THIS FIX TO YOUR VERSION OF EBASE:
> >-----------------------------------------
> >A) You should determine if you have this problem.
> >
> >-Get into ebase using your master password. Once you're on the HOME
> >screen, select: Scripts > Scriptmaker
> >
> >-From the Define Scripts for Names.102 dialog Double click on the Script
> >names "View Payments Script"
>
> I find this but the name does not include the word "script."
>
> >
> >-In the Script Definition for View Payments dialog the correct fourth
> >line
> >from the top should read:
> >If[not IsValid(All Payments All Names::Record Number)]
>
> I see the following
> If["not IsValid(All Payments All Names::Record Number)"]
>
> When I copy and paste the "correct" line, it still shows on screen
> with the quotes.
>
> >BUG IN EXPIRATION OF INDEFINITE MEMBERSHIPS
> >---------------------------------------------
>
> As of now, I have no pledges and no "indefinite memberrships.
>
> >
> >8) Problem with expiration of indefinite memberships
> >--------------------------------------------------------------------------
> >Fixed Bug where ebase, under some conditions, erroneously reported the
> >expiration of indefinite memberships as the last expiration date of a
> >past
> >full membership for that member. eBase now figures a changing future
> >date
> >for expiration of indefinite members based on system date.
> >-Double-click on the field named "Expire Date".
> >
> >-The "Specify Calculation" dialog box will appear. The correct
> >calculation for this field is as follows:
> >
> >Case(
> > Payment For <> "Dues", TextToDate(""),
> > IsEmpty(Start Date),TextToDate(""),
> > Duration = "Indefinite", Names::gToday+730,
> > Min(
> > Date(
> > Month(Start Date) +
> >If(PatternCount(Duration,"M"),TextToNum(LeftWords(Duration,1)),0),
> > Day(Start Date),
> > Year(Start Date) +
> >
> >If(PatternCount(Duration,"Y"),TextToNum(LeftWords(Duration,1)),0)),
> > Date(
> > Month(Start Date) + 1 +
> > If(PatternCount(Duration,"M"),TextToNum(LeftWords(Duration,1)),0),
> > 1,
> > Year(Start Date) +
> > If(PatternCount(Duration,"Y"),TextToNum(LeftWords(Duration,1)),0))
> >-
> >When I attempt to past this script and click on OK, it highlights
> >"Payment For" in the script and says this field can not be found.
>
> So it will not accept the change.
>
> >NEW FEATURE: DATA RECOVERY AND EXPORT UTILITY
> >----------------------------------------------
> >9) Added script to assist in data recovery/exporting to new ebase�
> >clones
> >--------------------------------------------------------------------------
> >
> Carl, I have a feeling this is important but it surely looks
> daunting. I can't imagine a situation however in which I'll be using
> ebase clones so maybe it's unimportant. Advice?
>
> Just FYI, you sent me the bug fix file on 3/18/02.
> --
> Simply,
>
> John
> mailto:[EMAIL PROTECTED]
> http://simsoc.org
>
> Thank you for you!
>
> ------------------
> Reminder to each recipient: To change your list account preferences, go to
> http://email.sparklist.com/scripts/lyris.pl?enter=support and enter the email
>address you used to subscribe to the ebase support list:: [EMAIL PROTECTED]
>
> To unsubscribe send a blank email to [EMAIL PROTECTED]
> ---------------------------------------------------------------------
> ebase - Relationship Management for Nonprofits, http://www.ebase.org
> ---------------------------------------------------------------------
--
Carl Paulsen
New Hampshire Rivers Council
54 Portsmouth Street
Concord, NH 03301
603-228-6472
603-228-0423 Fax
[EMAIL PROTECTED]
------------------
Reminder to each recipient: To change your list account preferences, go to
http://email.sparklist.com/scripts/lyris.pl?enter=support and enter the email address