On Sat, Aug 25, 2012 at 03:01:51PM +0200, berta...@ptitcanardnoir.org wrote:
> Following our discussions on the timeline for the next release, here is
> the plan we ended up with and I committed to send on this list :
> 
>   - Theoritically: ESR (August 28th) + 1 week = September 4th
>   - August 23: release 0.13~rc1, do the test suite together

Insert a "call for translation updates".

>   - Week 35
>     - Mon 27th: ESR is out
>                 update of the GnuPG docs
>   - Week 36
>     - Tue  4th: release 0.13~rc2, testing phase

Insert a "call for translation quality assurance and minor fixes".

>     - Thu  6th: monthly meeting
>   - Week 37
>     - Tue 11th: release 0.13 (final)

Please remember that the test suite needs to be done before pushing the
final image.

-- 