Attendees: Stephen, Elliot, Victor, Belen, Michael, David, Brian, Tiago, 
Mihail, Alex


Updates:

Elliot: Working on the upgrade to Django 1.8. Working on the database locking 
issues. Good discussion on how Elliot is using Django to access the database to 
keep locking problems from happening.

Victor: Working on toaster issues.

Belén: Working on the new theme. Uploaded design for 8422. Working with Michael 
on bug 7828.

Michael: Working on bug 7828.  Added patches for testing bugs.  Did a patch on 
the Bitbake URL issue. Working on 8527 and 8128.

David: No much toaster work this week. Asked some questions about image 
customization, that were answered.

Brian: Made comments on Ed's patch. Back and forth with Michael about the 
lsupdates issue

Tiago: Worked on remaining issues with CSS integration.

Mihail: Worked on automating remaining manual test for Toaster.

Alex: Working test plan.


Triage 
bugs:https://wiki.yoctoproject.org/wiki/Bug_Triage#YP_Toaster_Bugs_needing_Triage


Link to the wiki:

https://wiki.yoctoproject.org/wiki/Toaster_and_bitbake_communications


AR's:

Brian - Do an investigation of lsupdates command and possible conflicts. (Done)

Brian - Talk to Jessica about image customization issues. (In Process)

Alex - Set up a meeting to discuss the toaster testing report. (Done)

Brian - Review Ed's 2-modes patches. (Done)

Elliot - Share the scripts for changes to the new theme (with a branch in 
poky-contrib). (Done)

----

Belén: update Bugzilla with the decision about lsupdates


Opens:

Alex - QA Test plan for Toaster 2.1.  Reviewed document at:

https://docs.google.com/a/intel.com/document/d/1RN6t-_HfaVWKfcMD4DCl8RYwX_yfsnPcugXVMYz02GE/edit?usp=sharing

lsupdates: build information is probably more accurate than the information 
provided by the layer index. But the advantage of allowing updating layer index 
information is that Toaster will be able to learn about any new layers that are 
added to it. So a possible solution would be not to update existing layers, but 
bring in any new ones. We agree that this could be done. Belén will comment on 
the corresponding Bugzilla entry to make sure we don't forget about it.

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
*   Work Telephone:          (503) 712-0534
*    Cell:                                (208) 244-4460
* Email:                             [email protected]

-- 
_______________________________________________
toaster mailing list
[email protected]
https://lists.yoctoproject.org/listinfo/toaster

Reply via email to