District SSA office has completed assement and estimation for the
mehdipatnam school class rooms construction.

As per the telephonic conversation with G. Ramakrishna Reddy (Deputy
executive engineer), they have come up with an estimation of 5.4 Lakhs.

Next step is administrative approval from Collector, once that is done we
will cross the possible bottleneck of election code problems.

As communicated earlier the project will be excuted (once the approvals are
done) with 20: 80 basis (TMAD and Government).

Will speak to Mr. Srinivas Reddy garu(not sure of the exct designation, but
he is head of the SSA  district office, opposite CARE
hospital,Nampally) tomorrow.


-- 