Hi, Here is a quick update. District SSA office has completed assement and estimation for the mehdipatnam school class rooms construction.
As per the telephonic conversation with G. Ramakrishna Reddy (Deputy executive engineer), they have come up with an estimation of 5.4 Lakhs. Next step is administrative approval from Collector, once that is done we will cross the possible bottleneck of election code problems. As communicated earlier the project will be excuted (once the approvals are done) with 20: 80 basis (TMAD and Government). Will speak to Mr. Srinivas Reddy garu(not sure of the exct designation, but he is head of the SSA district office, opposite CARE hospital,Nampally) tomorrow. -- Regards... Harinath http://harinath.in