Also, please keep in mind that the goals estimates for the milestones
are not based on scoping out the required work for achieving the
milestone. The first two are roughly part of the GSOC project, which is
what their timeline goals are based on. The other will need a thorough
requirement breakdown, scope, and triage to be able to assign informed
timelines to them.
Thanks,
Jeff
El 6/18/14 2:23 p.m., Jeff Beatty escribió:
Hi everyone,
I've been doing a lot of thinking on what the milestones for the
Intellego platform should be. I will continue to do so before our
meeting tomorrow, refining and adding more details as time goes on,
but I wanted to give everyone some time to look at what I've written
down and come up with questions and ideas for making this better defined.
I utilized the tech spec etherpad to add this info to:
https://intellego.etherpad.mozilla.org/tech-spec-process-model
Thanks,
Jeff
--
*Jeff Beatty*
Localization Engineer
@mozilla_l10n <http://twitter.com/mozilla_l10n>
801.367.3763
_______________________________________________
tools-l10n mailing list
[email protected]
https://lists.mozilla.org/listinfo/tools-l10n