Attendees:
Eugene Chan
Valentina Birsan
Christophe Telep
Matthew Mings
Current Project Status:
4.2 Release Plan :
4.2 Enhancement Requests:
Iteration 3 - We are in week 4 of a 6 week iteration that ends 5/26. This iteration is for bug fixes and finish up a few enhancements.
Bugzilla 130765 (Matt) “ARM instrumentation”: Added to 4.2 plan as a Tech preview. (Approved by PMC, March 13rd)
Probekit (engine and UI) has been checked it, to be integrated into the build this week. Test cases created.
AspectJ implementation work done, to be integrated into the build this week. Test cases created.
Documentation still need to be created
Bugzilla 129095 (Valentina): “Line level coverage”. Code completed. Tech Preview available for download. Documentation need to be updated. Test cases to be created this week.
4.2 Defects backlog
All Blocking, Critical, Major and Normal opened defects must be fixed in 4.2
5 defects opened to be fixed during i2
Other Topics:
Reminder: The last day for major doc changes is tomorrow Wed May 10 EOD.
Copyright Statements: make sure to fix them before the end of this week. See the latest build report for file with missing copyright statements.
Plugin versioning: Bugzilla 138073: Eugene to track this work.
Weekly meeting Day & Time:
Weekly meeting will occur on Mondays at 8am PST, 11am EST, 4pm GMT, 5pm most of Europe.