Ilias Lazaridis wrote:
> I've notices that the milestone 0.11 contains many tasks:
>
> http://trac.edgewall.org/milestone/0.11
>
> Wouldn't it be preferable to split this work into a few more
> milestones?
>
> This could be of benefit (in order to avoid similar delays as with the
> actual 0.10 version).
>
> 0.11 - Focusing on Genshi Migration
...

within this thread...

CONTRIBUTION - Would like to do some work on the Genshi Migration
http://groups.google.com/group/trac-dev/browse_frm/thread/a0932139d50ad20a

... the teem seems to agree to a 'Genshi Centric' 0.11 milestone

the milestone entries have changed, too:

http://trac.edgewall.org/milestone/0.11

The roadmap should show more concise information, thus interested
contributors get immediately an overview.

* the section "Likely to be post-poned even more:", should be moved to
0.12 (including related tickets).
* the entries within the milestone should start with (wiki)pointers to
working-plans which contain actual 'help-needed' sections (thus
contributors can immediately get an overview of how to assist for a
functionality of their interest)
* the milestone 0.11 should get a date (e.g. 2006-12-29)

It is of course still possible to move solved 0.12 tickets back(!) to
the milestone 0.11 -this  would btw. have an motivating effect (not
like the negative feeling of having to post-pone something)

.

--
http://lazaridis.com


--~--~---------~--~----~------------~-------~--~----~
You received this message because you are subscribed to the Google Groups "Trac 
Development" group.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to [EMAIL PROTECTED]
For more options, visit this group at http://groups.google.com/group/trac-dev
-~----------~----~----~----~------~----~------~--~---

Reply via email to