On Fri, Jul 18, 2008 at 9:09 AM, Kai Behncke <[EMAIL PROTECTED]> wrote:
> > Dear users, > I succesfully installed trac. > If I click on "roadmap" I can now see my milestone, but how can I make an > entrie that I have done the work of that milestone at e.g. 30% ?? > It`s always at 0 % and I don`t know how to change. > > Thank you very much, Kai > That percentage is based on tickets assigned to the milestone. If you have two tickets and one is complete, you're 50% there. A little simplistic way to look at it, but that's how it is. Aaron (Note: I am only experienced in Trac <= 0.10.) --~--~---------~--~----~------------~-------~--~----~ You received this message because you are subscribed to the Google Groups "Trac Users" group. To post to this group, send email to [email protected] To unsubscribe from this group, send email to [EMAIL PROTECTED] For more options, visit this group at http://groups.google.com/group/trac-users?hl=en -~----------~----~----~----~------~----~------~--~---