Hi,

Am Montag, 3. Februar 2014 10:24:41 UTC+1 schrieb Kristian Nørgaard:
>
> I like the BurndownChart, but it only shows a drop in hours when a ticket 
> completes.
>

You need to set this in trac.ini

[estimation-tools]
estimation_field = remaininghours

Then it counts down the time you estimate as the remaining work. This can 
highly vary from your originally planned time. Of course, you need to 
periodically rejudge each ticket for how long you expect the work may still 
take. My experience is it's enought to go through the project ticket list 
once in a week. That depends on how fine-granular your plan is, and for how 
long you schedule your release date. 

CU, F@lk

-- 
You received this message because you are subscribed to the Google Groups "Trac 
Users" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to [email protected].
To post to this group, send email to [email protected].
Visit this group at http://groups.google.com/group/trac-users.
For more options, visit https://groups.google.com/groups/opt_out.

Reply via email to