Hello all,
I am attempting to create a forcing function for air-flow rate in a simulation.
I want to use low air-velocity with no night ventilation over the winter
months, and higher air-flow rate during the summer days and low air flow rate
during summer nights. So what I am trying to achieve is not a start and stop
(ON, OFF) situation for the whole cycle. For example:
0-2160 hrs (winter)
07:00 -18:00 (200 m³/hr) Day ventilation (ON, OFF)
18:00 -07:00 (0 m³/hr) Night ventilation
2161-6552hrs (Summer);
07:00-18:00 (1000 m³/hr) (ON continuously at different air flow
rate)
18:00-07:00 (200 m³/hr)
6552 - 8760hrs
07:00 -18:00 (200 m³/hr) Day ventilation (ON, OFF)
18:00 -07:00 (0 m³/hr) Night ventilation
Any suggestions on how best to schedule such forcing function?
Abdullahi Ahmed (BSc. MSc.) Postgraduate researcher
School of the Environment
University of Brighton
Cockcroft Building
Lewes Rd.
Brighton
BN2 4GJ
Tel: +44 01273 643455
_______________________________________________
TRNSYS-users mailing list
[email protected]
https://www.cae.wisc.edu/mailman/listinfo/trnsys-users