On 17 Nov., 22:29, Bertrand Chenal <[email protected]> wrote:
> stephan wrote:
> > Hi all,
>
> > [...]
> > Concerning projects: Great, almost what I m looking for. Is it
> > possible to enter not only the cumulated hours, but also start and end
> > time?
>
> the project_plan module
> (http://hg.tryton.org/hgwebdir.cgi/modules/project_plan/) add start and
> end date, but also allow to assign task to employees, to level tasks
> (delay one task if assigned to somebody already busy), to define
> dependencies between tasks (and even between projects), it also computes
> early/late finish/start of tasks wrt to dependencies.
>
> So it's quite powerful but not yet released, this means: no guaranty of
> support, no migrations, not well tested, etc. It's not released because
> we are not sure that for some feature that's the right way to do it (e.g
> task leveling). IMHO this module also needs reports (PERT or Gantt chart
> and a workload chart per employee). So if you have time to evaluate it
> and share your impression or provide improvements, you are welcome.
>

That´s even more than I (have been) asked for. I´ll discuss it with my
customer, could well be that he agrees in testing.

CU

Stephan Reihle

> --
> Bertrand Chenal
>
> B2CK SPRL
> Rue de Rotterdam, 4
> 4000 Li ge
> Belgium
> Tel: +32 474 207 906
> Email: [email protected]
> Website:http://www.b2ck.com/

-- 
[email protected] mailing list

Reply via email to