> You need to produce in advance because production takes times. And also 
> you may need to make production in cascade. So the system can not know 
> until which date in the future does it need to look to see what needs to 
> be produced. The period allow to define from now up to which date it 
> will look the stock levels. 
>

Thanks for this detailed explanation. Regarding stock levels you mention 
here- do you mean stock levels of finished goods? 

 

> So the period should depend on your production delays and the number of 
> cascading production you could have. But also you must not give a too 
> big number if you do not want to produce too much in advance. 
>
> -- 
> Cédric Krier - B2CK SPRL 
> Email/Jabber: [email protected] <javascript:> 
> Tel: +32 472 54 46 59 
> Website: http://www.b2ck.com/ 
>

понедельник, 20 марта 2017 г., 1:25:05 UTC+2 пользователь Cédric Krier 
написал:
>
> On 2017-03-19 11:58, 'Artem Braga' via tryton wrote: 
> > Is it possible to get some use case where supply period at Production 
> > Configuration could be used? I've read module documentation 
> > here: 
> http://doc.tryton.org/4.2/modules/stock_supply_production/doc/index.html 
> > but the meaning of Supply Period is not so clear for me though. 
>
> You need to produce in advance because production takes times. And also 
> you may need to make production in cascade. So the system can not know 
> until which date in the future does it need to look to see what needs to 
> be produced. The period allow to define from now up to which date it 
> will look the stock levels. 
> So the period should depend on your production delays and the number of 
> cascading production you could have. But also you must not give a too 
> big number if you do not want to produce too much in advance. 
>
> -- 
> Cédric Krier - B2CK SPRL 
> Email/Jabber: [email protected] <javascript:> 
> Tel: +32 472 54 46 59 
> Website: http://www.b2ck.com/ 
>

-- 
You received this message because you are subscribed to the Google Groups 
"tryton" group.
To view this discussion on the web visit 
https://groups.google.com/d/msgid/tryton/d4293e9e-b7c1-446f-9c99-91f00995f923%40googlegroups.com.

Reply via email to