On Dec 12, 2007 10:03 AM, Simon Laws <[EMAIL PROTECTED]> wrote:

> On Dec 12, 2007 9:45 AM, Luciano Resende <[EMAIL PROTECTED]> wrote:
>
> > Following Ant's question, after you cut the first RC, development
> > would continue on trunk or on a branch ? Based on the timeframe and
> > considering we would still work on issues on the week of Jan 7th, I'd
> > recommend continue on trunk until sometime around end of year.
> >
> > On Dec 12, 2007 12:22 AM, ant elder <[EMAIL PROTECTED]> wrote:
> > > I don't think the tomcat deep integration, JMS, or distribution
> > structure
> > > changes would all be done by next week. Haven't seen much happening
> with
> > > jsonrpc references recently either. We do have all of the rest of this
> > year
> > > to continue development though right?
> > >
> > >    ...ant
> > >
> > >
> > > On Dec 11, 2007 10:59 PM, Simon Laws <[EMAIL PROTECTED]>
> wrote:
> > >
> > > > Hi
> > > >
> > > > Following on from the JIRA tidy up note here are a few high level
> > areas
> > > > that
> > > > I've seen activity on over the last few weeks and so may be ready to
> > go
> > > > for
> > > > release 1.1.
> > > >
> > > > Deep tomcat integration
> > > > Better JMS support
> > > > JAXB based POJO transformations.
> > > > More policy function
> > > > Modeling of client side java script components
> > > > JSONRPC reference binding
> > > > Better support for doman API suggested by assembly spec
> > > > Domain based and standalone node operation
> > > > Domain lookup for remote access to domain services.
> > > > Transactions
> > > > JPA
> > > > Class loading and OSGI
> > > > BPEL fixes
> > > > Distribution structure changes
> > > >
> > > > Can you fill in the detail and tell me what we can get in,
> i.e.addwhat is
> > > > missing from the list, add details to what is on the list, indicate
> > what
> > > > shouldn't be on the list. Think of this as forming the CHANGES text
> so
> > it
> > > > should look like [1]. Even better go and update the CHANGES doc:-)
> > > >
> > > > As a reminder here is the timeline I'm working to. I'm planning on
> > > > spending
> > > > next week working on the first RC. Building the distribution, fixing
> > > > samples, READMES, licenses etc. The objective being to have a
> release
> > > > candidate before I go away for the holidays for people to review at
> > their
> > > > leisure. This means that when everyone is back we can spend the week
> > > > beginning 7th Jan knocking it into shape until we get an RC we can
> > vote
> > > > on.
> > > > The following week, beginning 14th would also be taken up by voting
> > with a
> > > > view to releasing the week beginning 21st (or earlier if we get
> done).
> > > >
> > > > Does that still sound reasonable to everyone. Are there pieces of
> > function
> > > > that must be in 1.1. that can't be done in this timescale?
> > > >
> > > > Regards
> > > >
> > > > Simon
> > > >
> > > > [1]
> > > >
> > > >
> >
> http://svn.apache.org/repos/asf/incubator/tuscany/java/sca/distribution/src/main/release/CHANGES
> > > >
> > >
> >
> >
> >
> > --
> > Luciano Resende
> > Apache Tuscany Committer
> > http://people.apache.org/~lresende<http://people.apache.org/%7Elresende><
> http://people.apache.org/%7Elresende>
> > http://lresende.blogspot.com/
> >
> > ---------------------------------------------------------------------
> > To unsubscribe, e-mail: [EMAIL PROTECTED]
> > For additional commands, e-mail: [EMAIL PROTECTED]
> >
> > If people are agreed that any work that gets committed to trunk over the
> Christmas holidays is related to fixing up the content of the release
> candidate contents we finalize next week then I'm happy to keep that
> effort
> going on trunk with a view to cutting the branch including all of the
> fixes
> people have made when I get back on the 2nd Jan. We could hope to use this
> "RC0" to catch 90% of the release issues and reduce the pain a little for
> this 90% by allowing the fixes to happen in just one place.
>
> If people have other projects in mind that take the trunk in a different
> direction then I'll take a branch next week.
>
> Simon
>

Doing it next year sounds good to me, i've no plans to start on new stuff
not related to 1.1 over the break but i would find it useful to have that
time to finish things off.

   ...ant

Reply via email to