On 20/07/16 14:07, Alex Brooks wrote:
> Telecity Harbour Exchange 8/9 has been having some power issues -
> a UPS decided to fall over, kit all over the shop has had a power
> cut with some power subsequently being restored and kit rebooted.
> It would appear that BT's kit there has been affected most
> significantly. If I had to guess, it might have something to do
> with the ongoing upgrade work there to increase power capacity, but
> then again it could just be too hot.
> 
> In theory, Telehouse has the power back up again now, so these are 
> supposedly all residual problems caused by the initial power loss.

Did you mean Telehouse, rather than Telec^WEquinix?

- -- 
Tom Hill
Network Manager

Bytemark Hosting
http://www.bytemark.co.uk/
tel. +44 1904 890 890
-----BEGIN PGP SIGNATURE-----
Version: GnuPG v2

iQEcBAEBCAAGBQJXj3wiAAoJEH2fKbrp2sQ6MAsIANzy3XgmmJcbQfCJCM8TuMZp
w3UcAiPrxHN6QI/yYoHM8Spq9G2uSszIpbYHLZQxhyNPmdg+hkOTIN1Cc37q9SSc
dAMZ1MxHbH69PfoW6hVtKlAl6PunCtzoNwFSfcHGL0Bj2qnGP2m7fzfN4wkmf/cc
lKXw2+kJ4DaHl5x7RWCrvZNkKRbiym71X71bpcZ+3pNZnUBA3smt2AOSg2dzsvFS
Ee7QB4wxU4a/yDfkK3+41S+KPSBaG1FxnpnxugHHmwT9QJZZ3FaiSDBXoEhIJHTh
M2SoTMB8OvWPxHmII8MXayqR88Oru2wGWvp0ZWCkEpeTtr0GEWSEBGzXF03mRCI=
=dxRb
-----END PGP SIGNATURE-----

Reply via email to