:) currently, I have 15 data nodes. for some tests, I am trying to decommission until 8 nodes.
Now, the total dfs used size is 52 TB which is including all replicated blocks. from 15 to 8, total spent time is almost 4 days long. ;( someone mentioned that I don't need to decommission node by node. for this case, is there no problems if I decommissioned 7 nodes at the same time? 2013. 4. 2., 오후 12:14, Azuryy Yu <[email protected]> 작성: > I can translate it to native English: how many nodes you want to decommission? > > > On Tue, Apr 2, 2013 at 11:01 AM, Yanbo Liang <[email protected]> wrote: > You want to decommission how many nodes? > > > 2013/4/2 Henry JunYoung KIM <[email protected]> > 15 for datanodes and 3 for replication factor. > > 2013. 4. 1., 오후 3:23, varun kumar <[email protected]> 작성: > > > How many nodes do you have and replication factor for it. > > >