Hello all,

I have a problem with the Process2Process communication inside the ODE. 
Basically I need to implement a BPEL process that uses and implements the same 
WSDL. For example I have a service A with two methods request-response 
"createEntity" and one way "confirmCreation", I expect my process to call 
"createEntity" method and then wait untill the "confirmCreation" method will be 
called on it, however since ODE route all MEXes internaly despite the fact that 
process actually only implements one single operation "confirmCreation" I'm 
getting an MEX expire and failed state.

Would it be possible to fix the P2P communication so that it would only happen 
when ODE as a recipient side is able to handle the operation, otherwise just 
proceed with a call though Integration Layer.

Renat

Reply via email to