What does the Equipments->Calendar page do? Or what is it supposed to do?

I created a maintenance task for a piece of equipment, then went to the Calendar tab to see if the maintenance task appeared. It didn't.

I went to the Work Effort component and found the maintenance work effort, but it doesn't appear on the WE calendar either. Then I discovered the WE calendar doesn't display tasks, only events.

I went back to the Asset Maint component and dug into the calendar code. It seems the Asset Maint calendar displays the production capacity of the piece of equipment, not the scheduled maintenance for it. Does that make sense? It seems to me that an Asset Maintenance calendar should show maintenace tasks that are due, not how many widgets the equipment can create in an hour.

-Adrian