Following are the steps to assign a task to a team member.

1) Find Projects https://demo.hotwaxmedia.com/projectmgr/control/FindProject
2) Select any project. Lets say
https://demo.hotwaxmedia.com/projectmgr/control/projectView?projectId=9100
3) Find tasks under this project
https://demo.hotwaxmedia.com/projectmgr/control/EditProjectTasks?projectId=9100
4) Select any task. Lets say
https://demo.hotwaxmedia.com/projectmgr/control/taskView?workEffortId=9102
5) Select Resources.
https://demo.hotwaxmedia.com/projectmgr/control/EditTaskPartyAssigns?workEffortId=9102
6) Now Click Add under Add Resource Assignment Screenlet
7) Once you add, you see the assigned user in a list ( which is below the
Add Resource Assignment Screenlet)
8) Click on Task Summary
9) There you have a Task Team screenlet on top right position which show the
list of user(s) who are assigned to this task.


Hope this helps !
- Vikas

On Thu, Jul 3, 2008 at 5:31 PM, Pal InfoCom Technologies <
[EMAIL PROTECTED]> wrote:

>
> Created project & allocate resources to project. Now I want to assign a
> task
> of project to whom they are member of.  resources. Please let me know how
> to
> assign tasks to resources or team members of project
>
> Preeti
> Pal Infocom Technologies Pvt. Ltd.
>
> --
> View this message in context:
> http://www.nabble.com/Assignment-of-tasks-tp18257691p18257691.html
> Sent from the OFBiz - User mailing list archive at Nabble.com.
>
>

Reply via email to