I have found out why the Gantt Chart does not work(in my revision and on the 
904demo)

The problem is that, OFBiz is generating Items like this out of the tasklist in 
gantChart.ftl 
g.AddTaskItem(new JSGantt.TaskItem(9102,"task1","12/03/2007", 
"12/05/2007","009900", 
"/projectmgr/control/taskView?workEffortId=9102", 0 , "16.0 
Hrs", 0 , 0, 9101, 1));

if I change the above statically to this 

g.AddTaskItem(new JSGantt.TaskItem(9103,"task2","12/05/2007", 
"12/16/2007","009900", 
"/projectmgr/control/taskView?workEffortId=9103", 0 , "24.0 Hrs", 0 , 
0, 9101, 1, 9102));

the, the chart displays nicely.

Tracking it back to the code, I found  these in GantChart.groovy

     taskInfo.estimatedStartDate = 
UtilDateTime.toDateString(taskInfo.estimatedStartDate, "MM/dd/yyyy");
     taskInfo.estimatedCompletionDate = 
UtilDateTime.toDateString(taskInfo.estimatedCompletionDate, "MM/dd/yyyy");

I however can't seem to find a method on UtilDateTime that will avoid the 
encoding.

Whiles I can produce the patch, I think this is very trivial and should be 
fixed by an OFBiz Committer so it can go into the right branches and whatever 
is involved in making a change.

Regards

Farouk A




--- On Tue, 16/6/09, Torstein Hegbom <[email protected]> wrote:

From: Torstein Hegbom <[email protected]>
Subject: Gant-chart
To: [email protected]
Date: Tuesday, 16 June, 2009, 11:36 AM

I am testing the project manager application.

 

It seems to me that the project manager application gantt-diagram does not
display correctly. 

 

Am I wrong? It seems that the duration is not correctly calculated.

 

Look at the following link:

https://demo904.ofbiz.org/projectmgr/control/ganttChart?projectId=9000

 

Thanks,

Torstein Hegbom




      