Hi Deyan,

Just a logistic tip: the OFBiz MLs don't support attachments nor included 
images. When you need to put an image in a message please use another mean. 
Anyway I guess we all understood your point, thanks for the details

Jacques
  ----- Original Message ----- 
  From: Deyan Tsvetanov 
  To: Jacques Le Roux 
  Cc: [email protected] ; Hans Bakker ; [email protected] 
  Sent: Wednesday, April 07, 2010 10:41 AM
  Subject: Re: ofbiz entity sync.


  Hi guys, 

  so about the transaction log: 

  I have a table called TRANSLOG with the following structure: 


  CREATE TABLE translog
  (
    id bigserial NOT NULL,
    "table" character varying(30) NOT NULL,
    operation character varying(6) NOT NULL,
    "statement" character varying NOT NULL,
    created_on timestamp with time zone NOT NULL DEFAULT now(),
    CONSTRAINT id_fk PRIMARY KEY (id)
  )

  Records in the TRANSLOG table are being inserted by the triggers for the 
table we are "watching" for changes on INSERT, UPDATE and DELETE. 
  The STATEMENT column contains executable SQL statement which is generated by 
the trigger function. The following screenshot shows some data in the TRANSLOG 
table: 



  So every time some database action is performed on the tables we are 
"watching" we get a TRANSLOG entry. 

  Each translog entry has a sequence ID. So when we want to PUSH that 
transaction log to the main server we actually execute the statements ON the 
main server. We execute the statements wrapped in a transaction which gets 
rolled back if an error has occured. 

  The translog push gets invoked by a stored procedure which gets called by a 
scheduled reoccuring job in ofbiz. 
  For each sync SP execution we store a record in a table called 
TRANSLOG_EXEC_LOG . There we keep the currently reached translog_id so we know 
from where to start the next time
  when  the sync SP is invoked. 

  So in general that's the mechanism. Pretty simple to implement, pretty simple 
to troubleshoot and pretty error resistant . Here's the screenshot of 
TRANSLOG_EXEC_LOG: 



  The result message could be either OK or the DB error message - either a 
constraint error or some other error. We always know which was the last 
successfully executed statement ( 
  last_command_id ). If there is an error then we know at which statement the 
error has happened - the next after the last successful one. 

  That's all in general. 

  -- deyan

  -----Original Message-----
  From: Jacques Le Roux <[email protected]>
  Reply-to: "Jacques Le Roux" <[email protected]>
  To: Deyan Tsvetanov <[email protected]>, [email protected]
  Cc: Hans Bakker <[email protected]>, [email protected]
  Subject: Re: ofbiz entity sync.
  Date: Tue, 6 Apr 2010 12:31:49 +0200

   Hi Deyan,

  Thanks for your clear explanation and suggestion. As I'm busy with another 
stuff, I have quickly put your comment as a quote in OFBIZ-3333 .

  Jacques


    ----- Original Message ----- 
    From: Deyan Tsvetanov 
    To: Jacques Le Roux 
    Cc: Hans Bakker ; [email protected] 
    Sent: Tuesday, April 06, 2010 9:42 AM 
    Subject: Re: ofbiz entity sync. 



    Hi Sirs, 

    I'm sorry, i got lost for some time :)
    Things happen :)

    There was a lot of discussion on the topic, but the summary: 

    there are some major issues that CAN be fixed in the current 
implementation: error recovery - due to interrupted connection between the two 
servers, sync speed - RMI can be removed , etc. 

    There is however a major issue that CAN NOT be fixed in the current 
implementation: the list and sequence of entities to be synchronized gets 
created by entities' timestamp - date_created_tx and last_update_tx. It works 
as long as the clocks of all the syncing parties are in sync. You can easily 
achieve this by using NTP for example - reliable enough. But if the clock of 
one of the parties gets un-synced for just few minutes, and during those few 
minutes records get inserted or updated than you are in trouble. Syncing the 
clock back won't help you because you won't be able to sync the broken records 
due to foreign key constraint issues. Examples I could give but I guess you 
could think of such by yourselves :)

    So IMHO the best approach for synchronization is not the timestamp but the 
TRANSACTION LOG. This approach is used in all major databases - m$ $ql, oracle. 

    For a customer I've implemented a transaction log based on triggers and 
stored procedures. The transaction log, triggers and the stored procedures 
however I implemented only postgresql as that was the customer's database. It's 
easy to implement ms sql or oracle version though. It works perfectly, much 
much much faster than RMI, recovers if the sync process is interrupted , etc. 
My goal was to implement this mechanism using entity engine level triggers and 
eventually commit it, but unfortunately still pretty busy with other things so 
we don't have resources that can be dedicated to work on that task at the 
moment, we're trying to work out the world financial crisis :)

    So if you find what i say reasonable you could go ahead with the triggers 
and SPs. For that you need database that supports triggers - so mysql won't 
work :)

    That was just the first part. 

    The second part is to identify all the tables that you need to synchronize. 
Some of them will be only pulled, some of them  pushed only and some of them 
synced in both directions. Next you need to test, reset the database and  test 
again and again until you identify the correct list of the tables so your sync 
process doesn't end up with FK  insert / update errors. That is pretty easy but 
time consuming task - it takes few days to complete :)

    So that's all I can say for now, without getting your bored with details :)
    If you have other questions - go ahead :)

    Cheers, 
    Deyan

    -----Original Message-----
    From: Jacques Le Roux <[email protected]>
    Reply-to: "Jacques Le Roux" <[email protected]>
    To: Hans Bakker <[email protected]>, 
[email protected], [email protected]
    Subject: Re: ofbiz entity sync.
    Date: Sat, 3 Apr 2010 10:04:29 +0200


Hi Hans,

I put a comment with an abstract of the situation. Please let me know what you 
think to get the ball rolling

Thanks

Jacques

From: "Hans Bakker" <[email protected]>
> Hi Gentleman,
> 
> may i ask if there was any progress on this issue?
> 
> https://issues.apache.org/jira/browse/OFBIZ-3333
> 
> I added the following comment:
> 
> We have a customer using entity sync and experiencing the problems in
> this issue.
> 
> We are interested working with other parties on this subject. If there
> is already substantial work done we are interested to compensate
> financially for it.
> 
> Please let me know if there is any progress here.
> 
> regards,
> Hans
> 
> -- 
> http://www.antwebsystems.com : 
> Quality OFBiz support for competitive rates....
> 
>




Reply via email to