I have some issues/questions with the the project management module.

1. What does the  "schedule" button do.. when i hit it, it messes up the
start/end times for each task and phase, it should at least prompt the user.

2. The mouse over for the Gantt chart for each task shows the wrong task end
date, also the alignment of the chart is off, there should be a print to PDF
button for this page.

3. Where is the data for the information stored (which tables?) i have
looked around for this information using a sql browser but i couldn't find
any obviously named tables.

4. Can i un-complete a task?

Thanks All!
-- 