I have been planning to implement ofbiz for fabrication industry.
Here the raw materials involved in fabricating a window are measured in
terms of metres, some even in 'tube' (for foam).

For example, to fabricate a 60 cm x 100cm window, some of the raw materials
required will be -
1. "Inner Frame 5 Chambers 83 mm" - 2.9 m
2. "Frame 5 Chambers, 65 mm" - 3.2 m
3. "Reinforcement for Frame" - 1m
4. "Foam" - 0.5 tube

I am slightly confused as to how to configure raw materials in the catalog
and the BOM to ensure correct inventory levels.

If someone has some ideas/ guidance, please do share.

-- 
Regards,
Varun Bhansaly