Christian, Clearly this should be included as a comment on https://issues.apache.org/jira/browse/OFBIZ-5526.
Regards, Pierre Smits *ORRTIZ.COM <http://www.orrtiz.com>* Services & Solutions for Cloud- Based Manufacturing, Professional Services and Retail & Trade http://www.orrtiz.com On Tue, Feb 11, 2014 at 9:23 PM, Christian Carlow < [email protected]> wrote: > Currently if the sum of a production run task declarations is is not used > to determine the quantity produced of the task when completed. Instead the > task quantity produced is updated to the quantity to produced minus the > declared rejected quantities. So rejected quantity be declared in order > for a task's quantity produced to be less than it's quantity to produce. > > This issue seems to be a bug. What if a production run is created to > produce 2 but only 1 is declared while the other was returned as material. > Shouldn't the quantity produced be 1 and not 2 after the task is complete? >