Not sure if it is supposed to use the setting, but when you assign a supplier to a product you can do multiple suppliers.
I find it a bit odd that it lets you do multiple main suppliers (I would think it should only let you select one). But even with just one set as main, when you do a generate requirements using MRP it does not consider if one is set as main (I would have thought that is why there was the setting)? Maybe I am missing something, but seems like something is a bit amiss. I will probably modify both items (only allow one main, soif they pick main it unsets any others set as main) Have it use the main if auto assign is used or it is generated by MRP. ----- Joel Fradkin -- View this message in context: http://ofbiz.135035.n4.nabble.com/Supplier-set-for-product-not-using-main-setting-for-auto-assign-tp4655498.html Sent from the OFBiz - User mailing list archive at Nabble.com.